Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

85
Measures in this catchment
WINEP, current record
85
Still active
not yet past their date
0
Assumed complete
completion date has passed
21
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SO102511 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Billingshurst WTW
Due 2026-27Arun (U/S Pallingham)
08SO102691 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
BILLINGSHURST WWTW
Due 2026-27Arun (U/S Pallingham)
08SO102697 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
BRIDGEFOOT KIRDFORD WPS
Due 2026-27Kird
08SO102424 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Buriton WTW
Due 2026-27BURITON
08SO102702 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
BURITON WWTW
Due 2026-27Stanbridge Stream
08SO102410 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Bury WTW
Due 2026-27BURY
08SO102412 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Chiddingfold WTW
Due 2026-27Loxwood Stm-Hambledon Trb
08SO102717 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
CHIDDINGFOLD WWTW
Due 2026-27Loxwood Stm-Hambledon Trb
08SO102558 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
COLDWALTHAM WTW
Due 2026-27COLDWALTHAM
08SO102430 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Fernhurst WTW
Due 2026-27FERNHURST
08SO102745 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
FERNHURST WWTW
Due 2026-27Lod
08SO102560 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
FITTLEWORTH WTW
Due 2026-27FITTLEWORTH
08SO102747 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
FITTLEWORTH WWTW
Due 2026-27Western Rother
08SO102489 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Grayswood WTW
Due 2026-27GRAYSWOOD
08SO102764 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
GRAYSWOOD WWTW
Due 2026-27Loxwood/Chiddingfold Trib
08SO102491 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Horsham New WTW
Due 2026-27Arun Horsham
08SO102781 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
HORSHAM NEW WWTW
Due 2026-27Arun Horsham
08SO102518 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Liss WTW
Due 2026-27LISS SSO - 115920
08SO102797 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
LISS WWTW
Due 2026-27LISS SSO - 115920
08SO102473 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Loxwood WTW
Due 2026-27Loxwood Stream
08SO102798 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
LOXWOOD WWTW
Due 2026-27Loxwood Stream
08SO102494 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Lurgashall WTW
Due 2026-27LURGASHALL
08SO102800 · aU_MON3Monitoring
U_MON3b: MCERTS certified overflow operation monitor
LURGASHALL WWTW
Due 2026-27Lod
08SO102475 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Mannings Heath WTW
Due 2026-27MANNINGS HEATH
08SO102806 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
MANNINGS HEATH WWTW
Due 2026-27Arun Source
08SO102496 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Northchapel WTW
Due 2026-27Kird
08SO102830 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
NORTHCHAPEL WWTW
Due 2026-27Kird
08SO102438 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Petersfield WTW
Due 2026-27Stanbridge Stream
08SO102841 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
PETERSFIELD WWTW
Due 2026-27Stanbridge Stream
08SO102842 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
PETWORTH WWTW
Due 2026-27Loxwood Stm-Hambledon Trb
08SO102482 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Pulborough WTW
Due 2026-27Chilt
08SO102613 · aEPR_MON1Monitoring
Install MCERTS certified WTW (water treatment works) Total daily volume flow/max flow rate monitoring for the first time at (WSW) water supply works
Rogate WSW
Due 2026-27Western Rother Durford
08SO102498 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Rogate WTW
Due 2026-27ROGATE
08SO102858 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
ROGATE WWTW
Due 2026-27Western Rother
08SO102862 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
RUDGWICK RECREATION GROUND WPS
Due 2026-27Arun (U/S Pallingham)
08SO102501 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Slinfold WTW
Due 2026-27SLINFOLD
08SO102876 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
SLINFOLD WWTW
Due 2026-27Arun (U/S Pallingham)
08SO102522 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
South Ambersham WTW
Due 2026-27Western Rother
08SO102881 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
SOUTH AMBERSHAM WWTW
Due 2026-27Western Rother
08SO102502 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
South Harting WTW
Due 2026-27SOUTH HARTING
08SO102882 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
SOUTH HARTING WWTW
Due 2026-27Elsted Stream
08SO102526 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Storrington WTW
Due 2026-27Stor
08SO102895 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
STORRINGTON WWTW
Due 2026-27Stor
08SO102508 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Wisborough Green WTW
Due 2026-27WISBOROUGH GREEN
08SO102931 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
WISBOROUGH GREEN WWTW
Due 2026-27Kird
08SO101096 · bWFD_NDLS_Chem1No deterioration
Prevent any deterioration
Billingshurst WTW
Due 2026-27Arun (U/S Pallingham)
08SO101083 · aWFD_NDLS_Chem2No deterioration
Prevent any deterioration
Horsham WTW
Due 2026-27Arun Horsham
08SO104950 · otEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
BARNETTS BRIDGE GRAFFHAM CEO
Due 2027-28Western Rother
08SO104950 · qpEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
BILLINGSHURST SSO
Due 2027-28Arun (U/S Pallingham)
08SO104950 · qaEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
BURITON CEO
Due 2027-28Stanbridge Stream
08SO104950 · oxEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
CHIDDINGFOLD SSO
Due 2027-28Loxwood Stm-Hambledon Trb
08SO104028 · aWFD_INVInvestigation
Investigate the cause of the spills
Fernhurst WTW WFD_INV
Due 2027-28Lod
08SO104950 · onEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
FITTLEWORTH SSO
Due 2027-28Western Rother
08SO104950 · qmEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
GRAYSWOOD CSO
Due 2027-28Loxwood/Chiddingfold Trib
08SO104950 · qtEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
LOXWOOD SSO
Due 2027-28Loxwood Stream
08SO103808 · aWFD_INVInvestigation
Investigations for actions to improve water quality in terms of relevant WFD status objectives.
LOXWOOD WTW
Due 2027-28Loxwood Stream
08SO103810 · aWFD_INVInvestigation
Investigations for actions to improve water quality in terms of relevant WFD status objectives.
LURGASHALL WTW
Due 2027-28LURGASHALL
08SO104950 · qdEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
PETERSFIELD SSO
Due 2027-28Stanbridge Stream
08SO102617 · aWFD_INV_N-TalInvestigation
Investigation to assess treatment options for nitrogen. Pilot, Nutrem
Petersfield WTW
Due 2027-28Stanbridge Stream
08SO104950 · rdEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
PETWORTH CSO
Due 2027-28Western Rother
08SO104950 · phEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
SLINFOLD SSO
Due 2027-28Arun (U/S Pallingham)
08SO101096 · aWFD_IMP_CHEMImprovement
Deliver a physical improvement
Billingshurst WTW
Due 2029-30Arun (U/S Pallingham)
08SO103917 · aEnvAct_IMP2Improvement
Wetland + Lining
BURITON CEO
Due 2029-30Stanbridge Stream
08SO104056 · aWFD_IMP_MODImprovement
Amend P permit level - P removal
CHIDDINGFOLD
Due 2029-30Loxwood Stm-Hambledon Trb
08SO103903 · aEnvAct_IMP2Improvement
SuDS + Storage
CHIDDINGFOLD SSO
Due 2029-30Loxwood Stm-Hambledon Trb
08SO104049 · aWFD_NDNo deterioration
Amend Total P permit
CLAPHAM
Due 2029-30Black Ditch (W Sussex)
08SO104083 · aWFD_IMPmImprovement
Amend Total P permit
FERNHURST
Due 2029-30FERNHURST
08SO104035 · aWFD_NDNo deterioration
Amend WFD ND Ammonia permit
HORSHAM NEW
Due 2029-30Arun Horsham
08SO104085 · aWFD_IMPgImprovement
Amend Total P permit
KIRDFORD
Due 2029-30KIRDFORD
08SO100034 · aWFD_ND_WRFlowNo deterioration
The AMP7 Hardham sustainability investigation will determine the requirement for an AMP8 ecological resilience scheme, focused on in-river enhancements to individual reaches of the Lancing Brook and Hammer Stream. These enhancements would be to provide ecological resilience, for example by removing backwater effects, and improving fish passage.
Lancing Brook & Hammer Stream WFD ecological resilience scheme
Due 2029-30Hammer Stream (W. Sussex)
08SO104710 · aEnvAct_IMP1Improvement
Amend total P permit
Liss
Due 2029-30LISS SSO - 115920
08SO103924 · aEnvAct_IMP2Improvement
SuDS + Storage
LOXWOOD SSO
Due 2029-30Loxwood Stream
08SO104088 · aWFD_IMPgImprovement
Amend Total P permit
LURGASHALL
Due 2029-30LURGASHALL
08SO104088 · bU_IMP1Improvement
Replace descriptive with numerical BOD and SS permits
Lurgashall WTW
Due 2029-30LURGASHALL
08SO103939 · aEnvAct_IMP2Improvement
SuDS + Storage
PETERSFIELD SSO
Due 2029-30Stanbridge Stream
08SO104094 · aWFD_IMPgImprovement
Amend Total P permit
PETWORTH
Due 2029-30Haslingbourne Stream
08SO104097 · aWFD_IMPgImprovement
Amend Total P permit
ROGATE
Due 2029-30ROGATE
08SO103908 · aEnvAct_IMP2Improvement
Preferred option is SuDS and storage, but the costs are based on storage only
SLINFOLD SSO
Due 2029-30Arun (U/S Pallingham)
08SO104102 · aWFD_IMPgImprovement
Amend Total P permit
TILLINGTON
Due 2029-30Western Rother
08SO104107 · aWFD_IMPgImprovement
Amend Total P permit
WISBOROUGH GREEN
Due 2029-30WISBOROUGH GREEN
08SO103961 · aEnvAct_IMP2Improvement
Wetland + Lining
BARNETTS BRIDGE GRAFFHAM CEO
Due 2034-35Western Rother
08SO103922 · aEnvAct_IMP2Improvement
SuDS + Storage
BILLINGSHURST SSO
Due 2034-35Arun (U/S Pallingham)
08SO103935 · aEnvAct_IMP2Improvement
SuDS + Storage
FITTLEWORTH SSO
Due 2034-35Western Rother
08SO103945 · aEnvAct_IMP2Improvement
SuDS + Storage
PETWORTH CSO
Due 2034-35Western Rother
08SO103949 · aEnvAct_IMP4Improvement
Wetland + Lining
SOUTH HARTING SSO
Due 2034-35Elsted Stream

85 of 85 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.