← Chilton Polden Goose Lane O/s Collings

Spill evidence · River Hub

Chilton Polden Goose Lane O/s Collings

Combined sewer overflow · WXW00474 · feeds BURNHAM-ON-SEA / HIGHBRIDGE STW
Wet weather

The discharge

Spill day
Wednesday, 28 January 2026
Started
28 Jan 2026, 00:32
Ended
28 Jan 2026, 00:54
Duration
22 minutes
Receiving water
South Drain
Parish
Chilton Polden

Rainfall evidence

Daily rainfall at the matched gauge (Gold Corner) for the spill day and the days before. A spill is dry when every day in the window is ≤ 0.25 mm.

1-day window: Wet weather3-day window: Wet weather4-day window: Wet weather
DateRainfall
28/01/2026 (spill day)2.794 mmrain
27/01/20260.397 mmrain
26/01/202624.101 mmrain
25/01/20260.331 mmrain
24/01/20267.767 mmrain

River flow that day: 29.046 m³/s. Verify at the EA rainfall station.

Gauge proximity

Outlet (red) vs matched rain gauge (blue), 3.0 km apart. Closer means the rainfall reading is more representative of the overflow.

Loading map…

Severity & context

Bathing water
Not Applicable
Shellfish water
Not Applicable
Ahead of the works
Unknown (no works overflow data)
Method & provenance. Dry/wet classification is decided by rainfall at the nearest EA gauge — ≤ 0.25 mm on the spill day and each preceding day of the window (how we classify). Spill data: Environment Agency EDM (outlet WXW00474). Rainfall: EA Hydrology gauge 40e8abd2-f395-42c8-95b1-b22c3348b0b5_405278. A dry spill is precautionary evidence of a likely fault, not proof of an offence — we test the rainfall, not the works' flow. Generated by River Brue and Axe Data.
Spill evidence — Chilton Polden Goose Lane O/s Collings — River Brue and Axe Data