The discharge

Spill day
Saturday, 19 October 2024
Started
19 Oct 2024, 11:00
Ended
25 Oct 2024, 01:15
Duration
5 days 14 hours
Receiving water
South Drain
Parish
Edington

Rainfall evidence

Daily rainfall at the matched gauge (Gold Corner) for the spill day and the days before. A spill is dry when every day in the window is ≤ 0.25 mm.

1-day window: Wet weather3-day window: Wet weather4-day window: Wet weather
DateRainfall
19/10/2024 (spill day)2.332 mmrain
18/10/202427.662 mmrain
17/10/20240.006 mmdry
16/10/202418.083 mmrain
15/10/20248.134 mmrain

River flow that day: 17.071 m³/s. Verify at the EA rainfall station.

Gauge proximity

Outlet (red) vs matched rain gauge (blue), 3.5 km apart. Closer means the rainfall reading is more representative of the overflow.

Loading map…

Severity & context

Bathing water
Not Applicable
Shellfish water
Not Applicable
Ahead of the works
Unknown (no works overflow data)
EA annual return (2024)
99 counted spills · 1934 h total
Monitor uptime (2024)
100% operational
Method & provenance. Dry/wet classification is decided by rainfall at the nearest EA gauge — ≤ 0.25 mm on the spill day and each preceding day of the window (how we classify). Spill data: Environment Agency EDM (outlet WXW00193). Rainfall: EA Hydrology gauge 40e8abd2-f395-42c8-95b1-b22c3348b0b5_405278. A dry spill is precautionary evidence of a likely fault, not proof of an offence — we test the rainfall, not the works' flow. Generated by River Brue and Axe Data.