Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

50
Measures in this catchment
WINEP, current record
50
Still active
not yet past their date
0
Assumed complete
completion date has passed
10
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SO102529 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Beckley WTW
Due 2026-27BECKLEY
08SO102441 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Benenden WTW
Due 2026-27BENENDEN
08SO102685 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
BENENDEN WWTW
Due 2026-27Tributary of Newmill Channel upstream of Rolvenden
08SO102409 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Burwash Common WTW
Due 2026-27BURWASH COMMON
08SO102703 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
BURWASH COMMON WWTW
Due 2026-27Dudwell
08SO102514 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Burwash Village WTW
Due 2026-27BURWASH VILLAGE
08SO102516 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Crouch Farm Mayfield WTW
Due 2026-27CROUCH FARM MAYFIELD
08SO102725 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
CROUCH FARM MAYFIELD WWTW
Due 2026-27Coggins Mill Stream
08SO102563 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
HAWKHURST NORTH WTW
Due 2026-27Hexden Channel
08SO102776 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
HAWKHURST NORTH WWTW
Due 2026-27Hexden Channel
08SO102564 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
HAWKHURST SOUTH WTW
Due 2026-27Kent Ditch
08SO102777 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
HAWKHURST SOUTH WWTW
Due 2026-27Kent Ditch
08SO102470 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Hurst Green WTW
Due 2026-27HURST GREEN
08SO102569 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
IDEN WTW
Due 2026-27IDEN
08SO102435 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Meres Farm Mayfield WTW
Due 2026-27MERES FARM MAYFIELD
08SO104833 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
MILL CORNER NORTHIAM WTW
Due 2026-27MILL CORNER NORTHIAM
08SO102538 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Rolvenden Layne WTW
Due 2026-27ROLVENDEN LAYNE
08SO102859 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
ROLVENDEN LAYNE WWTW
Due 2026-27Hexden Channel
08SO102539 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Sandhurst WTW
Due 2026-27SANDHURST
08SO102865 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
SANDHURST WWTW
Due 2026-27Hexden Channel
08SO102589 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
TENTERDEN WTW
Due 2026-27Newmill Channel downstream of A28
08SO102902 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
TENTERDEN WWTW
Due 2026-27Newmill Channel downstream of A28
08SO104735 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Washwell Lane Wadhurst
Due 2026-27WASHWELL LANE WADHURST
08SO102917 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
WASHWELL LANE WADHURST WWTW
Due 2026-27Tidebrook
08SO102462 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Wittersham WTW
Due 2026-27WITTERSHAM
08SO101112 · bWFD_NDLS_Chem1No deterioration
Prevent any deterioration
Quickbourne Lane Northam STW
Due 2026-27Lower Rother from Etchingham to Scot's Float
08SO101089 · aWFD_NDLS_Chem2No deterioration
Prevent any deterioration
Quickbourne Lane WTW
Due 2026-27Lower Rother from Etchingham to Scot's Float
08SO104950 · pvEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
BURWASH COMMON SSO
Due 2027-28Dudwell
08SO104950 · pmEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
CASTLE TERRACE HAWKHURST CSO
Due 2027-28Hexden Channel
08SO103797 · aWFD_INVInvestigation
Investigations for actions to improve water quality in terms of relevant WFD status objectives.
CROUCH FARM MAYFIELD WTW
Due 2027-28CROUCH FARM MAYFIELD
08SO104950 · rEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
HAWKHURST NORTH SSO
Due 2027-28Hexden Channel
08SO104950 · peEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
HAWKHURST SOUTH SSO
Due 2027-28Kent Ditch
08SO103802 · aWFD_INVInvestigation
Investigations for actions to improve water quality in terms of relevant WFD status objectives.
HAWKHURST SOUTH WTW
Due 2027-28Kent Ditch
08SO103811 · aWFD_INVInvestigation
Investigations for actions to improve water quality in terms of relevant WFD status objectives.
MERES FARM MAYFIELD WTW
Due 2027-28MERES FARM MAYFIELD
08SO104950 · qbEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
MILL CORNER NORTHIAM CSO
Due 2027-28Lower Rother from Etchingham to Scot's Float
08SO103812 · aWFD_INVInvestigation
Investigations for actions to improve water quality in terms of relevant WFD status objectives.
MILL CORNER NORTHIAM WTW
Due 2027-28MILL CORNER NORTHIAM
08SO104950 · qEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
SANDHURST SSO
Due 2027-28Hexden Channel
08SO103826 · aWFD_INVInvestigation
Investigations for actions to improve water quality in terms of relevant WFD status objectives.
TICEHURST WTW
Due 2027-28Limden
08SO104074 · aWFD_IMPgImprovement
Amend Total P permit
BURWASH COMMON
Due 2029-30BURWASH COMMON
08SO104080 · aWFD_IMPgImprovement
Amend Total P permit
CROUCH FARM MAYFIELD
Due 2029-30CROUCH FARM MAYFIELD
08SO100126 · aEnvAct_IMP2Improvement
SuDS + Storage
HAWKHURST NORTH SSO
Due 2029-30HEXDEN CHANNEL
08SO104041 · aWFD_NDNo deterioration
Amend WFD ND BOD permit
HAWKHURST SOUTH
Due 2029-30Kent Ditch
08SO103918 · aEnvAct_IMP2Improvement
SuDS + Storage
MILL CORNER NORTHIAM CSO
Due 2029-30Lower Rother from Etchingham to Scot's Float
08SO101112 · aWFD_IMP_CHEMImprovement
Deliver a physical improvement
Quickbourne Lane Northam STW
Due 2029-30Lower Rother from Etchingham to Scot's Float
08SO104098 · aWFD_IMPmImprovement
Amend Total P permit
ROLVENDEN LAYNE
Due 2029-30ROLVENDEN LAYNE
08SO103957 · aEnvAct_IMP2Improvement
Wetland + Lining
SANDHURST SSO
Due 2029-30Hexden Channel
08SO104047 · aWFD_NDNo deterioration
Amend WFD ND BOD permit
TICEHURST
Due 2029-30Limden
08SO104104 · aWFD_IMPmImprovement
Amend Total P permit
WASHWELL LANE WADHURST
Due 2029-30WASHWELL LANE WADHURST
08SO103906 · aEnvAct_IMP2Improvement
SuDS + Storage
HAWKHURST SOUTH SSO
Due 2034-35Kent Ditch
08SO103960 · aEnvAct_IMP4Improvement
SuDS + Storage
QUICKBOURNE LANE NORTHIAM SSO
Due 2034-35Lower Rother from Etchingham to Scot's Float

50 of 50 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.