What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08SW104965 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) BITTAFORD STW | Due 2026-27 | Lud brook |
| 08SW104966 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) BITTAFORD STW | Due 2026-27 | Lud brook |
| 08SW104851 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) ERMINGTON STW | Due 2026-27 | Lower Erme |
| 08SW104850 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) ERMINGTON STW | Due 2026-27 | Lower Erme |
| 08SW102971 · a | HD_INV | Investigation | Investigation to confirm degree of impact on CSMG flow targets within the River Erme within the Dartmoor SAC. Investigation for improved fish passage at weir required too. Subject to confirmation with EA/NE Harford Moor, Erme | Due 2026-27 | Erme |
| 08SW104787 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) HOLBETON SEWAGETREATMENT WORKS | Due 2026-27 | ERME |
| 08SW104788 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) HOLBETON SEWAGETREATMENT WORKS | Due 2026-27 | ERME |
| 08SW104775 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Ivybridge STW | Due 2026-27 | Erme |
| 08SW104774 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Ivybridge STW | Due 2026-27 | Erme |
| 08SW104558 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) UGBOROUGH STW | Due 2026-27 | Lud Brook |
| 08SW104557 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) UGBOROUGH STW | Due 2026-27 | Lud Brook |
| 08SW102967 · j | EE_IMP | Improvement | Obstruction. Combined INV and IMP. Confirm EA ownership of gauging station Eel Obstruction - River Erme at Harford Moor | Due 2029-30 | Erme |
| 08SW100129 · c | BW_IMP3 | Improvement | 2 spills 50m3 aggregated HOLBETON STW_SSO_HOLBETON | Due 2029-30 | HOLBETON STW_SSO_HOLBETON |
13 of 13 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.