Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

80
Measures in this catchment
WINEP, current record
79
Still active
not yet past their date
1
Assumed complete
completion date has passed
33
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08WW100215 · bHD_IMPImprovement
Full options appraisal to determine the best value solution to the impact of Shrewton WRC on the local ecology.
Options appraisal for Shrewton WRC - Discharge Relocation
Complete 2025-26Till (Hampshire Avon)
08WW100628 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
All Cannings WRC - All Cannings SPS Flow Monitoring
Due 2026-27Etchilhampton Water
08WW100401 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
All Cannings WRC - All Cannings SPS Overflow Monitoring
Due 2026-27Etchilhampton Water
08WW100629 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
All Cannings WRC - Horton SPS Flow Monitoring
Due 2026-27Etchilhampton Water
08WW100632 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Amesbury WRC Flow Monitoring
Due 2026-27Hampshire Avon (Upper) d/s Nine Mile River confl
08WW100405 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Amesbury WRC Overflow Monitoring
Due 2026-27Hampshire Avon (Upper) d/s Nine Mile River confl
08WW100634 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Barford St Martin WRC Flow Monitoring
Due 2026-27Nadder (Middle)
08WW100407 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Barford St Martin WRC Overflow Monitoring
Due 2026-27Nadder (Middle)
08WW100099 · aWFD_NDINV_WRFlowInvestigation
Investigate effect of abstraction from Wessex Water's source at Bulbridge on the WFD status of River Nadder
Bulbridge WFD ND investigation
Due 2026-27Nadder (Middle)
08WW100671 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Collingbourne Ducis WRC - Collingbourne Ducis SPS Flow Monitoring
Due 2026-27Bourne (Hampshire Avon)
08WW100445 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Collingbourne Ducis WRC - Collingbourne Ducis SPS Overflow Monitoring
Due 2026-27Bourne (Hampshire Avon)
08WW100100 · aWFD_NDINV_WRFlowInvestigation
Investigate effect of abstraction from Wessex Water's source at Devizes Road on the WFD status of the Hampshire Avon (upper) d/s Nine Mile River confluence
Devizes Road WFD ND investigation
Due 2026-27Hampshire Avon (Upper) d/s Nine Mile River confl
08WW100093 · aWFD_NDINV_WRFlowInvestigation
Investigate effect of abstraction from Wessex Water's source at Fonthill Bishop on the WFD status of the Fonthill Stream and Teffont Brook
Fonthill Bishop WFD ND investigation
Due 2026-27Fonthill Stream
08WW100704 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Fovant WRC Flow Monitoring
Due 2026-27Fovant Brook
08WW100478 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Fovant WRC Overflow Monitoring
Due 2026-27Fovant Brook
08WW100712 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Great Wishford WRC Flow Monitoring
Due 2026-27Wylye (Lower)
08WW100486 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Great Wishford WRC Overflow Monitoring
Due 2026-27Wylye (Lower)
08WW100727 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Hurdcott WRC Flow Monitoring
Due 2026-27Bourne (Hampshire Avon)
08WW100499 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Hurdcott WRC Overflow Monitoring
Due 2026-27Bourne (Hampshire Avon)
08WW100102 · aWFD_NDINV_WRFlowInvestigation
Investigate effect of abstraction from Wessex Water's source at Leckford Bridge on the WFD status of the Bourne (Hampshire Avon)
Leckford Bridge WFD ND investigation
Due 2026-27Bourne (Hampshire Avon)
08WW100743 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Maiden Bradley WRC Flow Monitoring
Due 2026-27Wylye (Headwaters)
08WW100515 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Maiden Bradley WRC Overflow Monitoring
Due 2026-27Wylye (Headwaters)
08WW100888 · aU_MON4Monitoring
MCERTS certified Flow passed forward flow monitor (U_MON4e)
MONKTON DEVERILL WRC flow monitoring
Due 2026-27Wylye (Headwaters)
08WW100866 · aU_MON3Monitoring
MCERTS certified overflow operation monitor (U_MON3b)
MONKTON DEVERILL WRC overflow monitoring
Due 2026-27Wylye (Headwaters)
08WW100768 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Pewsey WRC Flow Monitoring
Due 2026-27Hampshire Avon (East) and Woodborough Stream
08WW100540 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Pewsey WRC Overflow Monitoring
Due 2026-27Hampshire Avon (East) and Woodborough Stream
08WW100778 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Ratfyn WRC Flow Monitoring
Due 2026-27Hampshire Avon (Upper) d/s Nine Mile River confl
08WW100551 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Ratfyn WRC Overflow Monitoring
Due 2026-27Hampshire Avon (Upper) d/s Nine Mile River confl
08WW100793 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Shrewton WRC Flow Monitoring
Due 2026-27Till (Hampshire Avon)
08WW100566 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Shrewton WRC Overflow Monitoring
Due 2026-27Till (Hampshire Avon)
08WW100823 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Warminster WRC Flow Monitoring
Due 2026-27Wylye (Headwaters)
08WW100597 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Warminster WRC Overflow Monitoring
Due 2026-27Wylye (Headwaters)
08WW100402 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
WRC - Farm SPS Overflow Monitoring
Due 2026-27Etchilhampton Water
08WW101000 · hfEnvAct_INV4Investigation
Storm overflows - Investigations
***A-WINEP*** CAMP ROAD SPS SO Investigation (14311B)
Due 2027-28Till (Hampshire Avon)
08WW101000 · hgEnvAct_INV4Investigation
Storm overflows - Investigations
***A-WINEP*** FARM PUMPING STATION SO Investigation (14058B)
Due 2027-28Etchilhampton Water
08WW101000 · heEnvAct_INV4Investigation
Storm overflows - Investigations
***A-WINEP*** HINDON WASTEWATER TREATMENT WORKS SO Investigation (13149C)
Due 2027-28Fonthill Stream
08WW100053 · aWFD_INV_CHEMInvestigation
Ecotoxicological study of Ratfyn WRC discharge (Hampshire Avon)
4g Local investigation Ratfyn WRC - Discharge Investigation
Due 2027-28Hampshire Avon (Upper) d/s Nine Mile River confl
08WW101000 · fmEnvAct_INV4Investigation
Storm overflows - Investigations
BARFORD ST MARTIN WRC SO Investigation (13015S)
Due 2027-28Nadder (Middle)
08WW101000 · cwEnvAct_INV4Investigation
Storm overflows - Investigations
CALVESWATER PUMPING STATION SO Investigation (14439B)
Due 2027-28Wylye Trib (The Were or Swan)
08WW101000 · hxEnvAct_INV4Investigation
Storm overflows - Investigations
COLLINGBOURNE DUCIS PUMPING STATION SO Investigation (14050B)
Due 2027-28Bourne (Hampshire Avon)
08WW101000 · coEnvAct_INV4Investigation
Storm overflows - Investigations
FOVANT WATER RECYCLING CENTRE SO Investigation (13129S)
Due 2027-28Fovant Brook
08WW101000 · cxEnvAct_INV4Investigation
Storm overflows - Investigations
GREAT WISHFORD WRC SO Investigation (13353S)
Due 2027-28Wylye (Lower)
08WW101000 · iqEnvAct_INV4Investigation
Storm overflows - Investigations
HINDON PUMPING STATION SO Investigation (14346B)
Due 2027-28Fonthill Stream
08WW101000 · cuEnvAct_INV4Investigation
Storm overflows - Investigations
HURDCOTT WASTEWATER TREATMENT WORKS SO Investigation (13158S)
Due 2027-28Bourne (Hampshire Avon)
08WW101000 · ndEnvAct_INV4Investigation
Storm overflows - Investigations
LAKE PLEASURE GARDENS CSO
Due 2027-28Wylye Trib (The Were or Swan)
08WW101000 · cdEnvAct_INV4Investigation
Storm overflows - Investigations
MAIDEN BRADLEY WWTW SO Investigation (13191C)
Due 2027-28Wylye (Headwaters)
08WW101000 · cvEnvAct_INV4Investigation
Storm overflows - Investigations
SHREWTON WATER RECYCLING CENTRE SO Investigation (13275S)
Due 2027-28Till (Hampshire Avon)
08WW101000 · hqEnvAct_INV4Investigation
Storm overflows - Investigations
SPANIEL'S BRIDGE PUMPING STATION SO Investigation (14047B)
Due 2027-28Etchilhampton Water
08WW102062 · aHD_IMP_NNImprovement
Improvements to WRC to achieve tightened phosphorus permit.
Amesbury WRC - Phosphorus Removal
Due 2029-30Hampshire Avon (Upper) d/s Nine Mile River confl
08WW101002 · dyEnvAct_IMP2Improvement
EnvAct_IMP4dy. Storm overflows - Frequency improvements
BARFORD ST MARTIN WRC SO improvement (13015S)
Due 2029-30Nadder (Middle)
08WW102063 · aHD_IMPImprovement
Improvements to WRC to achieve tightened phosphorus permit.
Bishops Cannings (All Cannings) WRC - Phosphorus Removal
Due 2029-30Etchilhampton Water
08WW101002 · biEnvAct_IMP4Improvement
EnvAct_IMP4bi. Storm overflows - Frequency improvements
CALVESWATER PUMPING STATION SO improvement (14439B)
Due 2029-30Wylye Trib (The Were or Swan)
08WW101002 · weEnvAct_IMP4Improvement
Storm overflows - Wetland treatment solution.
COATE, SPANIELS BRIDGE (Site ID 14047B)
Due 2029-30Etchilhampton Water
08WW100230 · aDrWPA_IMPImprovement
Improvements to WRC to achieve new nitrogen permit.
Collingbourne Ducis WRC - Nitrogen Removal
Due 2029-30Bourne (Hampshire Avon)
08WW103022 · aWFD_IMPmImprovement
Improvements to WRC (or alternative catchment option) to achieve tightened phosphorus permit.
East Knoyle WRC - Phosphorus Removal
Due 2029-30Sem
08WW101002 · wcEnvAct_IMP4Improvement
Storm overflows - Wetland treatment solution.
FARM (Site ID 14058B)
Due 2029-30Etchilhampton Water
08WW101002 · baEnvAct_IMP4Improvement
EnvAct_IMP4ba. Storm overflows - Frequency improvements
FOVANT WATER RECYCLING CENTRE SO improvement (13129S)
Due 2029-30Fovant Brook
08WW102067 · aHD_IMP_NNImprovement
Improvements to WRC to achieve tightened phosphorus permit.
Great Wishford WRC - Phosphorus Removal
Due 2029-30Wylye (Lower)
08WW101002 · bjEnvAct_IMP2Improvement
EnvAct_IMP4bj. Storm overflows - Frequency improvements
GREAT WISHFORD WRC SO improvement (13353S)
Due 2029-30Wylye (Lower)
08WW101002 · bgEnvAct_IMP2Improvement
EnvAct_IMP4bg. Storm overflows - Frequency improvements
HURDCOTT WASTEWATER TREATMENT WORKS SO improvement (13158S)
Due 2029-30Bourne (Hampshire Avon)
08WW102068 · aHD_IMP_NNImprovement
Improvements to WRC to achieve tightened phosphorus permit.
Hurdcott WRC - Phosphorus Removal
Due 2029-30Bourne (Hampshire Avon)
08WW100231 · aWFDGW_IMPImprovement
Improvements to WRC to achieve new nitrogen permit.
Maiden Bradley WRC - Nitrogen Removal
Due 2029-30Wylye (Headwaters)
08WW103023 · aHD_IMPImprovement
Improvements to WRC (or alternative catchment option) to achieve tightened phosphorus permit.
Marden WRC - Phosphorus Removal
Due 2029-30Hampshire Avon (West)
08WW102069 · aHD_IMP_NNImprovement
Improvements to WRC to achieve tightened phosphorus permit.
Netheravon WRC - Phosphorus Removal
Due 2029-30Hampshire Avon (Upper) u/s Nine Mile River confl
08WW102070 · aHD_IMP_NNImprovement
Improvements to WRC to achieve tightened phosphorus permit.
Pewsey WRC - Phosphorus Removal
Due 2029-30Hampshire Avon (East) and Woodborough Stream
08WW100214 · aHD_IMPImprovement
Discharge relocation from WRC, to upstream in river, to improve river flow upstream of abstraction.
Ratfyn WRC - Discharge Relocation
Due 2029-30Hampshire Avon (Upper) d/s Nine Mile River confl
08WW102071 · aHD_IMP_NNImprovement
Improvements to WRC to achieve tightened phosphorus permit.
Ratfyn WRC - Phosphorus Removal
Due 2029-30Hampshire Avon (Upper) d/s Nine Mile River confl
08WW103065 · aU_IMP1Improvement
Change from descriptive to numerical permit, with associated improvements to WRC (notably sanitary limits and flow measurement). Site <250pe but numerical permit required as WRC gaining phosphorus permit limit.
Semley WRC - Numerical Permit
Due 2029-30Sem
08WW103062 · aWFD_IMPmImprovement
Improvements to WRC to achieve new phosphorus permit.
Semley WRC - Phosphorus removal
Due 2029-30Sem
08WW101002 · bhEnvAct_IMP2Improvement
EnvAct_IMP4bh. Storm overflows - Frequency improvements
SHREWTON WATER RECYCLING CENTRE SO improvement (13275S)
Due 2029-30Till (Hampshire Avon)
08WW100215 · aHD_IMPImprovement
Discharge relocation from WRC to improve river water quality in winterbourne stretch.
Shrewton WRC - Discharge Relocation
Due 2029-30Till (Hampshire Avon)
08WW102074 · aHD_IMP_NNImprovement
Improvements to WRC to achieve tightened phosphorus permit.
Shrewton WRC - Phosphorus Removal
Due 2029-30Till (Hampshire Avon)
08WW103067 · aU_IMP1Improvement
Change from descriptive to numerical permit, with associated improvements to WRC (notably sanitary limits and flow measurement). Site <250pe but numerical permit required as WRC gaining phosphorus permit limit.
Stanton St Bernard WRC - Numerical Permit
Due 2029-30Etchilhampton Water
08WW103024 · aHD_IMPImprovement
Improvements to WRC (or alternative catchment option) to achieve new phosphorus permit.
Stanton St Bernard WRC - Phosphorus Removal
Due 2029-30Etchilhampton Water
08WW101002 · whEnvAct_IMP4Improvement
Storm overflows - Wetland treatment solution.
TILSHEAD, CAMP ROAD (Site ID 14311B)
Due 2029-30Till (Hampshire Avon)
08WW102075 · aHD_IMP_NNImprovement
Improvements to WRC to achieve tightened phosphorus permit.
Tisbury WRC - Phosphorus Removal
Due 2029-30Nadder (Middle)
08WW103063 · aHD_IMPImprovement
Improvements to WRC to achieve new phosphorus permit.
Upavon WRC - Phosphorus removal
Due 2029-30Hampshire Avon (Upper) u/s Nine Mile River confl
08WW102076 · aHD_IMP_NNImprovement
Improvements to WRC to achieve tightened phosphorus permit.
Warminster WRC - Phosphorus Removal
Due 2029-30Wylye (Headwaters)
08WW103066 · aU_IMP1Improvement
Change from descriptive to numerical permit, with associated improvements to WRC (notably sanitary limits and flow measurement). Site <250pe but numerical permit required as WRC gaining phosphorus permit limit.
Wedhampton WRC - Numerical Permit
Due 2029-30Etchilhampton Water
08WW103064 · aHD_IMPImprovement
Improvements to WRC to achieve new phosphorus permit.
Wedhampton WRC - Phosphorus removal
Due 2029-30Etchilhampton Water

80 of 80 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.