Before the works
An overflow that spills while its own treatment works stays shut is not being overwhelmed by rain — the problem is upstream of the works, and local.
If the sewer network were genuinely overwhelmed by rainfall, the treatment works' own storm overflow would be discharging too.
When an upstream overflow spills on a day its works did not, the works still had capacity — so the discharge points to a blockage, a failed pump, or infiltration on that branch, not to a works too small for its catchment. That changes who pays and how fast: a branch fault is maintenance, chargeable now, not a capital scheme waiting for the next five-year price review.
| Overflow | Events | Its works | On record |
|---|---|---|---|
| Rosanna Sailing School Wootton, - 100599CSO | 73 | Sandown, Ventnor,bembridge STW | No measure |
| Dodnor Ceo - 108516 | 64 | Sandown, Ventnor,bembridge STW | No measure |
| Fairlee Road Newport Outside 62, - 108507CSO | 37 | Sandown, Ventnor,bembridge STW | No measure |
| School Green Road Freshwater Ceo - 108522 | 35 | Sandown, Ventnor,bembridge STW | No measure |
| Fairlee, - 111781CSO | 34 | Sandown, Ventnor,bembridge STW | No measure |
| Bow Bridge Freshwater Ceo - 108512 | 34 | Sandown, Ventnor,bembridge STW | No measure |
| Main Road Porchfield Ceo - 108550 | 23 | Sandown, Ventnor,bembridge STW | No measure |
| Kings Manor Ceo - 108530 | 15 | Sandown, Ventnor,bembridge STW | No measure |
| Coastguard Lane Freshwater Bay Ceo - 108521 | 14 | Sandown, Ventnor,bembridge STW | No measure |
| The Point Bembridge New Ceo - 110194 | 11 | Sandown, Ventnor,bembridge STW | No measure |
| Luccombe Ceo - 110208 | 10 | Sandown, Ventnor,bembridge STW | No measure |
| Medina Road Cowes Ceo - 108537 | 10 | Sandown, Ventnor,bembridge STW | No measure |
| Hope Beach Shanklin New Ceo - 109389 | 8 | Sandown, Ventnor,bembridge STW | No measure |
| Albany Road East Cowes Ceo - 116071 | 4 | Sandown, Ventnor,bembridge STW | No measure |
| Lion Point Ventnor Ceo - 108546 | 4 | Sandown, Ventnor,bembridge STW | No measure |
| Eastern Gardens Sandown Ceo - 108039 | 3 | Sandown, Ventnor,bembridge STW | No measure |
| Mill Road Yarmouth, - 108538CSO | 3 | Sandown, Ventnor,bembridge STW | No measure |
| Norton Green Ceo - 108543 | 2 | Sandown, Ventnor,bembridge STW | No measure |
| Floating Bridge Cowes, - 109300CSO | 2 | Sandown, Ventnor,bembridge STW | No measure |
| The Duver St Helens Ceo - 108561 | 1 | Sandown, Ventnor,bembridge STW | No measure |
| School Green Road Freshwater Outside 33, - 108554CSO | 1 | Sandown, Ventnor,bembridge STW | No measure |
| Shanklin Chine, - 108046CSO | 1 | Sandown, Ventnor,bembridge STW | No measure |
What this needs to be reliable
The comparison needs both monitors working. Where a works' own overflow monitor was offline we record no result rather than a pre-works spill, so this is a floor. A treatment works itself is excluded — it is the end of the line and cannot spill before the works. Two works in the catchment have no monitored overflow at all, so their upstream overflows are listed as not assessed, not as clean.