Reduction tracker
Is each overflow actually spilling less? The reduction plan won't tell you per overflow — so we measure it from the spill record.
What the plan is, and what it leaves out
The Storm Overflows Discharge Reduction Plan is the government's plan — published in 2022 and expanded in September 2023 — to cut how often England's storm overflows discharge. It sets deadlines by category, not by overflow:
- By 2035 — overflows near every designated bathing water, and 75% of those near high-priority nature sites, must be improved.
- By 2045 — the remaining high-priority overflows.
- By 2050 — every storm overflow, with discharges capped at around 10 spills a year regardless of location.
The targets are due to be reviewed in 2027 — a commitment in the plan, not a statutory duty. But the plan sets no target for any individual overflow and publishes no per-overflow progress — only these whole-category deadlines, and it doesn't even publish which specific overflows are high-priority. So there is no official way to ask “is this overflow on track?” This page builds that view from the Environment Agency's EDM record: each overflow's counted spills per year — the EA's own 12/24-hour block figure, the same basis the cap is written in — against its 2020 baseline and the 2050 cap of ~10, with the deadline its location implies.
Every overflow against its cap
Ranked by the latest full year's spills. The deadline is derived from proximity to a designated site — indicative, not an official per-overflow target. The dotted line on each trajectory is the 10-spills cap.
| Overflow | Deadline | Baseline | Latest | Since baseline | vs cap | Trajectory | Verdict |
|---|---|---|---|---|---|---|---|
| Golberdon STWSO SBB00495 | 2050 | 151 | 126 83 events | -17% | 12.6× | Falling — behind | |
| Haye Road, CallingtonCSO SBB00550 | 2050 | 72 | 77 151 events | +7% | 7.7× | Rising | |
| Callington STWSSO SBB00202 | 2050 | 73 | 62 28 events | -15% | 6.2× | Falling — behind | |
| Rilla Mill STWSO SBB01026 | 2050 | 366 | 38 50 events | -90% | 3.8× | Falling — behind | |
| Quethiock STWSO SBB01003 | 2050 | 278 | 34 23 events | -88% | 3.4× | Falling — behind | |
| Pillaton STWSSO SBB00937 | 2050 | 119 | 33 19 events | -72% | 3.3× | Falling — behind | |
| Bathpool STWSO SBB00079 | 2050 | 20 ·24 | 26 12 events | +30% | 2.6× | Rising | |
| Hatt STWSSO SBB00547 | 2050 | 68 | 24 18 events | -65% | 2.4× | Falling — behind | |
| Pensilva pumping stationPS-CSO/EO SBB00927 | 2050 | 28 | 22 15 events | -21% | 2.2× | Falling — behind | |
| North Hill STWSO SBB00840 | 2050 | 153 | 19 20 events | -88% | 1.9× | Falling — behind | |
| Blunts S T STW, TidefordSO SBB00122 | 2050 | 15 ·24 | 11 4 events | -27% | 1.1× | Nearly there |
What this is — and what it is not
This is River Hub's measurement, not the plan's. The reduction plan publishes no target for an individual overflow and no per-overflow progress — so we compare each outlet's counted spills to its 2020 baseline and the 10/year cap. Counted spills use the Environment Agency's 12/24-hour block method — the figure the cap is actually written in — taken from the published annual return where we have it and computed the same way for the current year; the smaller “events” figure beneath each is River Hub's count of discrete discharges over 15 minutes, shown for context. The deadline shown is derived by proximity to a designated site, not an official determination, and the plan is a policy commitment rather than a statutory duty. A falling trend is progress, but only ≤10 by the deadline is compliance. Where 2020 data is thin the baseline falls back to the earliest year on record, shown beside it. How the two counts differ →