Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

19
Measures in this catchment
WINEP, current record
19
Still active
not yet past their date
0
Assumed complete
completion date has passed
4
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08WW100640 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Blagdon WRC Flow Monitoring
Due 2026-27Yeo - source to conf Congresbury Yeo
08WW100413 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Blagdon WRC Overflow Monitoring
Due 2026-27Yeo - source to conf Congresbury Yeo
08WW100877 · aU_MON4Monitoring
MCERTS certified Flow passed forward flow monitor (U_MON4e)
BUTCOMBE WRC flow monitoring
Due 2026-27BUTCOMBE STORM TANK
08WW100426 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Butcombe WRC Overflow Monitoring
Due 2026-27BUTCOMBE STORM TANK
08WW100819 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Ubley WRC Flow Monitoring
Due 2026-27Yeo - source to conf Congresbury Yeo
08WW100593 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Ubley WRC Overflow Monitoring
Due 2026-27Yeo - source to conf Congresbury Yeo
08WW100849 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Wrington WRC Flow Monitoring
Due 2026-27Yeo - source to conf Congresbury Yeo
08WW100624 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Wrington WRC Overflow Monitoring
Due 2026-27Yeo - source to conf Congresbury Yeo
08WW101000 · ecEnvAct_INV4Investigation
Storm overflows - Investigations
BLAGDON WASTEWATER TREATMENT WORKS SO Investigation (13025S)
Due 2027-28Yeo - source to conf Congresbury Yeo
08WW101000 · eeEnvAct_INV4Investigation
Storm overflows - Investigations
BUTCOMBE WATER RECYCLING CENTRE SO Investigation (13042S)
Due 2027-28BUTCOMBE STORM TANK
08WW101000 · kqEnvAct_INV4Investigation
Storm overflows - Investigations
HARBOUR ROAD CSO SO Investigation (16838C)
Due 2027-28Portbury Ditch - source to conf R Severn Estuary
08WW101000 · dqEnvAct_INV4Investigation
Storm overflows - Investigations
LANGFORD PUMPING STATION SO Investigation (15580B)
Due 2027-28Yeo - source to conf Congresbury Yeo
08WW101000 · edEnvAct_INV4Investigation
Storm overflows - Investigations
UBLEY WATER RECYCLING CENTRE SO Investigation (13319S)
Due 2027-28Yeo - source to conf Congresbury Yeo
08WW101000 · dgEnvAct_INV4Investigation
Storm overflows - Investigations
WRINGTON COMBINED SEWER OVERFLOW SO Investigation (17058C)
Due 2027-28Yeo - source to conf Congresbury Yeo
08WW101000 · obEnvAct_INV4Investigation
Storm overflows - Investigations
WRINGTON WATER RECYCLING CENTRE SSO
Due 2027-28Yeo - source to conf Congresbury Yeo
08WW101002 · coEnvAct_IMP4Improvement
EnvAct_IMP4co. Storm overflows - Frequency improvements
BLAGDON WASTEWATER TREATMENT WORKS SO improvement (13025S)
Due 2029-30Yeo - source to conf Congresbury Yeo
08WW101002 · cqEnvAct_IMP2Improvement
EnvAct_IMP4cq. Storm overflows - Frequency improvements
BUTCOMBE WATER RECYCLING CENTRE SO improvement (13042S)
Due 2029-30BUTCOMBE STORM TANK
08WW101002 · ccEnvAct_IMP4Improvement
EnvAct_IMP4cc. Storm overflows - Frequency improvements
LANGFORD PUMPING STATION SO improvement (15580B)
Due 2029-30Yeo - source to conf Congresbury Yeo
08WW101002 · cpEnvAct_IMP2Improvement
EnvAct_IMP4cp. Storm overflows - Frequency improvements
UBLEY WATER RECYCLING CENTRE SO improvement (13319S)
Due 2029-30Yeo - source to conf Congresbury Yeo

19 of 19 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.