Reduction tracker

Is each overflow actually spilling less? The reduction plan won't tell you per overflow — so we measure it from the spill record.

What the plan is, and what it leaves out

The Storm Overflows Discharge Reduction Plan is the government's plan — published in 2022 and expanded in September 2023 — to cut how often England's storm overflows discharge. It sets deadlines by category, not by overflow:

  • By 2035 — overflows near every designated bathing water, and 75% of those near high-priority nature sites, must be improved.
  • By 2045 — the remaining high-priority overflows.
  • By 2050 — every storm overflow, with discharges capped at around 10 spills a year regardless of location.

The targets are due to be reviewed in 2027 — a commitment in the plan, not a statutory duty. But the plan sets no target for any individual overflow and publishes no per-overflow progress — only these whole-category deadlines, and it doesn't even publish which specific overflows are high-priority. So there is no official way to ask “is this overflow on track?” This page builds that view from the Environment Agency's EDM record: each overflow's counted spills per year — the EA's own 12/24-hour block figure, the same basis the cap is written in — against its 2020 baseline and the 2050 cap of ~10, with the deadline its location implies.

10
Above the 2050 cap
of 11 tracked
6
Rising since baseline
trend is the wrong way
0
On a 2035 deadline
near a bathing water
1
Within the cap
≤10 spills in 2025

Every overflow against its cap

Ranked by the latest full year's spills. The deadline is derived from proximity to a designated site — indicative, not an official per-overflow target. The dotted line on each trajectory is the 10-spills cap.

OverflowDeadlineBaselineLatestSince baselinevs capTrajectoryVerdict
Gratton, YelvertonCSO
SBB00514
205063
167
248 events
+165%16.7×Rising
Gratton STW, YelvertonSSO
SBB00515
205033
143
718 events
+333%14.3×Rising
Plymouth Rd Opp Dingle Rd, PlymptonCSO
SBB00946
205082
88
96 events
+7%8.8×Rising
Glenholt pumping station, PlymouthPS-CSO/EO
SBB00493
205087
67
122 events
-23%6.7×Falling — behind
Lake Ln, DouslandCSO
SBB00656
205028 ·24
46
77 events
+64%4.6×Rising
Market Road, PlymptonCSO
SBB00747
205050
46
56 events
-8%4.6×Falling — behind
Meavy S T STW, DouslandSO
SBB00757
205014 ·24
34
21 events
+143%3.4×Rising
Clearbrook STWSSO
SBB00272
20502 ·24
26
23 events
+1200%2.6×Rising
Glenview, YelvertonCSO
SBB00333
205030 ·24
26
26 events
-13%2.6×Falling — behind
Newnham Road, ColebrookCSO
SBB00833
205064
22
16 events
-66%2.2×Falling — behind
Moorland Rd, PlymouthCSO
SBB00801
20501 ·25
1
1 events
0%0.1×—Within the cap

What this is — and what it is not

This is River Hub's measurement, not the plan's. The reduction plan publishes no target for an individual overflow and no per-overflow progress — so we compare each outlet's counted spills to its 2020 baseline and the 10/year cap. Counted spills use the Environment Agency's 12/24-hour block method — the figure the cap is actually written in — taken from the published annual return where we have it and computed the same way for the current year; the smaller “events” figure beneath each is River Hub's count of discrete discharges over 15 minutes, shown for context. The deadline shown is derived by proximity to a designated site, not an official determination, and the plan is a policy commitment rather than a statutory duty. A falling trend is progress, but only ≤10 by the deadline is compliance. Where 2020 data is thin the baseline falls back to the earliest year on record, shown beside it. How the two counts differ →