What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08SO102400 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Ardingly WTW | Due 2026-27 | ARDINGLY |
| 08SO102675 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor ARDINGLY WWTW | Due 2026-27 | Ouse Ardingly to confluence with Scrase Brk |
| 08SO102403 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Balcombe WTW | Due 2026-27 | BALCOMBE |
| 08SO102679 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor BALCOMBE WWTW | Due 2026-27 | Ouse from Slaugham to Ardingly Resevoir |
| 08SO102680 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor BARCOMBE NEW WWTW | Due 2026-27 | Bevern Stream |
| 08SO102510 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Berwick WTW | Due 2026-27 | BERWICK |
| 08SO102406 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Blackboys WTW | Due 2026-27 | BLACKBOYS |
| 08SO102693 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor BLACKBOYS WWTW | Due 2026-27 | Tickerage Stream |
| 08SO102411 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Buxted WTW | Due 2026-27 | BUXTED |
| 08SO102706 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor BUXTED WWTW | Due 2026-27 | Uck Upstream of Buxted |
| 08SO102413 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Danehill WTW | Due 2026-27 | DANEHILL |
| 08SO102728 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor DANEHILL WWTW | Due 2026-27 | Sheffield Park Stream |
| 08SO102428 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils Ditchling WTW | Due 2026-27 | DITCHLING |
| 08SO102729 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor DITCHLING WWTW | Due 2026-27 | Bevern Stream |
| 08SO102468 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Halland WTW | Due 2026-27 | HALLAND |
| 08SO102769 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor HALLAND WWTW | Due 2026-27 | Ridgewood Stream |
| 08SO102778 · a | U_MON3 | Monitoring | U_MON3b: MCERTS certified overflow operation monitor HEADCORN WWTW | Due 2026-27 | Middle Ouse |
| 08SO102469 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Horsted Keynes WTW | Due 2026-27 | HORSTED KEYNES |
| 08SO102783 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor HORSTED KEYNES WWTW | Due 2026-27 | Cockhaise Brook |
| 08SO102471 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Kingston Hollow WTW | Due 2026-27 | KINGSTON HOLLOW |
| 08SO102790 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor KINGSTON HOLLOW WWTW | Due 2026-27 | Iford Marshes |
| 08SO102476 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Maresfield WTW | Due 2026-27 | MARESFIELD |
| 08SO102807 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor MARESFIELD WWTW | Due 2026-27 | Shortbridge Stream |
| 08SO102822 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor NEAVES LANE RINGMER WWTW | Due 2026-27 | Glynde Reach |
| 08SO102436 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Newick WTW | Due 2026-27 | Middle Ouse |
| 08SO102829 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor NEWICK WWTW | Due 2026-27 | Middle Ouse |
| 08SO102479 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Nutley WTW | Due 2026-27 | NUTLEY |
| 08SO102483 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Ripe WTW | Due 2026-27 | RIPE |
| 08SO102856 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor RIPE WWTW | Due 2026-27 | Glynde Reach |
| 08SO102581 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils SCAYNES HILL WTW | Due 2026-27 | Middle Ouse |
| 08SO102867 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor SCAYNES HILL WWTW | Due 2026-27 | Middle Ouse |
| 08SO102587 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils STAPLEFIELD WTW | Due 2026-27 | STAPLEFIELD |
| 08SO102888 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor STAPLEFIELD WWTW | Due 2026-27 | Ouse from Slaugham to Ardingly Resevoir |
| 08SO102485 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Uckfield WTW | Due 2026-27 | Ridgewood Stream |
| 08SO102911 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor UCKFIELD WWTW | Due 2026-27 | Ridgewood Stream |
| 08SO104839 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring WEST HOATHLY WTW | Due 2026-27 | WEST HOATHLY |
| 08SO104776 · a | U_MON3 | Monitoring | U_MON3b: MCERTS certified overflow operation monitor White Hart Buxted WPS | Due 2026-27 | Tributary of River Uck north of Uckfield |
| 08SO104777 · a | U_MON4 | Monitoring | U_MON4e: MCERTS certified Flow passed forward flow monitor including civils White Hart Buxted WPS | Due 2026-27 | Tributary of River Uck north of Uckfield |
| 08SO102599 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils Wivelsfield WTW | Due 2026-27 | WIVELSFIELD |
| 08SO101094 · a | WFD_NDLS_Chem2 | No deterioration | Prevent any deterioration Uckfield WTW | Due 2026-27 | Uck at Uckfield |
| 08SO101093 · a | WFD_NDLS_Chem2 | No deterioration | Prevent any deterioration Uckfield WTW | Due 2026-27 | Uck at Uckfield |
| 08SO104950 · pn | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact BARCOMBE NEW SSO | Due 2027-28 | Bevern Stream |
| 08SO104950 · oz | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact BUXTED SSO | Due 2027-28 | Uck Upstream of Buxted |
| 08SO104950 · pr | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact DANEHILL SSO | Due 2027-28 | Sheffield Park Stream |
| 08SO100043 · q | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact DITCHLING SSO | Due 2027-28 | BEVERN STREAM |
| 08SO100043 · ai | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact HALLAND SSO | Due 2027-28 | RIDGEWOOD STREAM |
| 08SO104950 · aj | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact HAYLIND ROAD HAYWARDS HEATH CSO | Due 2027-28 | WESTERN ROAD HAYWARDS HEATH CSO - 108811 |
| 08SO104950 · ar | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact HORSTED KEYNES CEO | Due 2027-28 | COCKHAISE BROOK |
| 08SO104950 · ou | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact HORSTED KEYNES SSO | Due 2027-28 | Cockhaise Brook |
| 08SO103804 · a | WFD_INV | Investigation | Investigations for actions to improve water quality in terms of relevant WFD status objectives. KINGSTON HOLLOW WTW | Due 2027-28 | KINGSTON HOLLOW |
| 08SO104804 · a | WFD_INV | Investigation | Investigations for actions to improve water quality in terms of relevant WFD status objectives. KINGSTON HOLLOW WTW | Due 2027-28 | KINGSTON HOLLOW |
| 08SO104950 · pl | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact NEAVES LANE RINGMER SSO | Due 2027-28 | Glynde Reach |
| 08SO104950 · bo | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact NOAHS ARK LANE LINDFIELD CEO | Due 2027-28 | NOAHS ARK LANE LINDFIELD CEO - 108290 |
| 08SO104950 · fj | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact PELHAM ROAD LINDFIELD CSO | Due 2027-28 | WESTERN ROAD HAYWARDS HEATH CSO - 108811 |
| 08SO104950 · ca | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact PENN CRESCENT HAYWARDS HEATH CSO | Due 2027-28 | WESTERN ROAD HAYWARDS HEATH CSO - 108811 |
| 08SO104950 · cb | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact PENN CRESCENT HAYWARDS HEATH OUTSIDE CSO | Due 2027-28 | WESTERN ROAD HAYWARDS HEATH CSO - 108811 |
| 08SO104950 · cd | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact PORTSMOUTH LANE LINDFIELD CEO | Due 2027-28 | MILL GREEN ROAD HAYWARDS HEATH CSO - 108287 |
| 08SO103815 · a | WFD_INV | Investigation | Investigations for actions to improve water quality in terms of relevant WFD status objectives. RODMELL WTW | Due 2027-28 | Iford Marshes |
| 08SO103823 · a | WFD_INV | Investigation | Investigations for actions to improve water quality in terms of relevant WFD status objectives. WIVELSFIELD WTW | Due 2027-28 | WIVELSFIELD |
| 08SO104032 · a | WFD_ND | No deterioration | Amend WFD ND Ammonia permit BARCOMBE NEW | Due 2029-30 | Bevern Stream |
| 08SO104032 · b | WFD_ND | No deterioration | Amend WFD ND BOD permit BARCOMBE NEW | Due 2029-30 | Bevern Stream |
| 08SO103912 · a | EnvAct_IMP2 | Improvement | SuDS + Storage BARCOMBE NEW SSO | Due 2029-30 | Bevern Stream |
| 08SO104072 · a | WFD_IMPg | Improvement | Amend Total P permit BERWICK | Due 2029-30 | BERWICK |
| 08SO104081 · a | WFD_IMPm | Improvement | Amend Total P permit DITCHLING | Due 2029-30 | DITCHLING |
| 08SO100127 · a | EnvAct_IMP2 | Improvement | SuDS + Storage HAYLIND ROAD HAYWARDS HEATH CSO | Due 2029-30 | WESTERN ROAD HAYWARDS HEATH CSO - 108811 |
| 08SO104045 · a | WFD_ND | No deterioration | Amend WFD ND BOD permit NEWICK | Due 2029-30 | Middle Ouse |
| 08SO100161 · a | EnvAct_IMP2 | Improvement | Screen Only (IMP5) NOAHS ARK LANE LINDFIELD CEO | Due 2029-30 | NOAHS ARK LANE LINDFIELD CEO - 108290 |
| 08SO104091 · a | WFD_IMPm | Improvement | Amend Total P permit NUTLEY | Due 2029-30 | NUTLEY |
| 08SO100171 · a | EnvAct_IMP2 | Improvement | SuDS + Storage PELHAM ROAD LINDFIELD CSO | Due 2029-30 | WESTERN ROAD HAYWARDS HEATH CSO - 108811 |
| 08SO100172 · a | EnvAct_IMP2 | Improvement | Screen Only (IMP5) PENN CRESCENT HAYWARDS HEATH a CSO | Due 2029-30 | WESTERN ROAD HAYWARDS HEATH CSO - 108811 |
| 08SO100173 · a | EnvAct_IMP2 | Improvement | Screen Only (IMP5) PENN CRESCENT HAYWARDS HEATH OUTSIDE CSO | Due 2029-30 | WESTERN ROAD HAYWARDS HEATH CSO - 108811 |
| 08SO100175 · a | EnvAct_IMP2 | Improvement | Screen Only (IMP5) PORTSMOUTH LANE LINDFIELD CEO | Due 2029-30 | MILL GREEN ROAD HAYWARDS HEATH CSO - 108287 |
| 08SO104067 · a | WFD_IMPg | Improvement | Amend Total P permit SLAUGHAM | Due 2029-30 | Ouse from Slaugham to Ardingly Resevoir |
| 08SO104067 · b | U_IMP1 | Improvement | Replace descriptive with numerical BOD and SS permits Slaugham WTW | Due 2029-30 | Ouse from Slaugham to Ardingly Resevoir |
| 08SO101093 · b | WFD_ND_CHEM3 | No deterioration | Prevent any deterioration Uckfield WTW | Due 2029-30 | Uck at Uckfield |
| 08SO103954 · a | EnvAct_IMP4 | Improvement | Wetland + Lining HALLAND SSO | Due 2034-35 | Ridgewood Stream |
| 08SO103911 · a | EnvAct_IMP2 | Improvement | SuDS + Storage NEAVES LANE RINGMER SSO | Due 2034-35 | Glynde Reach |
77 of 77 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.