Why it keeps happening

Treatment works capacity

Every overflow goes to a sewage treatment works that serves a fixed area. There is no public data available to understand if the works has sufficient capacity to treat the sewage for the local population. We estimate this capacity based on the required capacity in the EA permit compared to the local population estimated to be on the sewage system. As we receive data on the actual processing capacity from South West Water we will add that too.

Capacity across the River Taw

Of the works we could assess, Weare Giffard STW is estimated to take more flow than its permit allows — it serves about 368 people. 29 more can’t be assessed yet: River Hub has no permit for them.

1
Over their permitted flow
of the 1 works we could assess
0
Have headroom but spill anyway
of the 1 assessed: points to another problem
29
Cannot be assessed yet
no permit loaded
368
People on an over-loaded works
among the works we could assess
Works
Load against permit
Overflow at works
Spare capacity
Weare Giffard STW
368 people · 34 m³/day permitted (from WINEP)
WINEP says the permit needs a detailed evaluation, due by May 2030.
151%
Over capacity
1,338 h
0 upstream
None
at or over its permit
Parracombe STW
306 people · permit not found
Not known
Not assessed
7 h
0 upstream
Not known
South Molton STW
6,090 people · permit not found
Not known
Not assessed
2,524 h
6 upstream · 12 pre-STW
Not known
Morchard Bishop STW
1,041 people · permit not found
Not known
Not assessed
443 h
1 upstream · 5 pre-STW
Not known
West Buckland STW
505 people · permit not found
Not known
Not assessed
1,006 h
0 upstream
Not known
Knowstone East STW
231 people · permit not found
Not known
Not assessed
181 h
0 upstream
Not known
Molland West STW
254 people · permit not found
Not known
Not assessed
72 h
0 upstream
Not known
Zeal Monachorum STW
408 people · permit not found
Not known
Not assessed
1,886 h
0 upstream
Not known
Atherington STW
422 people · permit not found
Not known
Not assessed
522 h
0 upstream
Not known
Riddlecombe S T STW
492 people · permit not found
Not known
Not assessed
48 h
0 upstream
Not known
Cobbaton STW
824 people · permit not found
Not known
Not assessed
1,527 h
0 upstream
Not known
Lapford STW
1,118 people · permit not found
Not known
Not assessed
369 h
3 upstream · 4 pre-STW
Not known
Chawleigh STW
640 people · permit not found
Not known
Not assessed
837 h
0 upstream
Not known
Kings Nympton North STW
446 people · permit not found
Not known
Not assessed
7 h
0 upstream
Not known
Burrington STW
523 people · permit not found
Not known
Not assessed
568 h
1 upstream · 1 pre-STW
Not known
Spreyton STW
520 people · permit not found
Not known
Not assessed
1,683 h
0 upstream
Not known
Yeo Mill S T STW
187 people · permit not found
Not known
Not assessed
37 h
0 upstream
Not known
Middle Marwood STW
8,680 people · permit not found
Not known
Not assessed
0 h
2 upstream · 274 pre-STW
Not known
Chittlehamholt STW
180 people · permit not found
Not known
Not assessed
884 h
0 upstream
Not known
Ashreigney STW
492 people · permit not found
Not known
Not assessed
1,488 h
0 upstream
Not known
High Bickington STW
1,005 people · permit not found
Not known
Not assessed
1,812 h
0 upstream
Not known
Bishops Nympton STW
1,106 people · permit not found
Not known
Not assessed
30 h
0 upstream
Not known
Goodleigh STW
393 people · permit not found
Not known
Not assessed
1 h
0 upstream
Not known
Brayford STW
407 people · permit not found
Not known
Not assessed
3,762 h
0 upstream
Not known
Alswear No 2 S T Septnk Alswear
170 people · permit not found
Not known
Not assessed
62 h
0 upstream
Not known
Wembworthy New STW
254 people · permit not found
Not known
Not assessed
872 h
0 upstream
Not known
Bratton Fleming STW
174 people · permit not found
Not known
Not assessed
1,192 h
0 upstream
Not known
North Tawton STW
2,116 people · permit not found
Not known
Not assessed
1,163 h
2 upstream · 1 pre-STW
Not known
Stoke Rivers STW
174 people · permit not found
Not known
Not assessed
0 h
0 upstream
Not known
Bow STW
408 people · permit not found
Not known
Not assessed
11 h
0 upstream
Not known

The black line marks 100% of permitted dry-weather flow; a dashed empty bar means no permit was found to measure against. Load is an estimate — population served × per-head water use, plus infiltration — not a permit-compliance finding. A works over 100% here is a signal to investigate, not a proven breach. Overflow hours are the works' own storm overflow in the last full year. Where a works’ permit isn’t loaded, its permitted flow may come from WINEP, the regulator’s list of required improvements (marked “from WINEP”); that figure is used only when it fits our population estimate, and a loaded permit always takes its place.

29 works with no permit loaded

River Hub doesn’t yet hold the permits for Parracombe STW, South Molton STW, Morchard Bishop STW, West Buckland STW, Knowstone East STW, Molland West STW and 23 more, so it can’t check whether they are big enough for the people they serve. That’s a gap, not a clean bill of health, and it’s the quickest thing on this page to fix: discharge permits are public, and the Environment Agency must supply them on request. No request for them has been published on River Hub yet.

  1. Look a works up on the EA’s public register of discharge permits.
  2. Ask the Environment Agency for them through WhatDoTheyKnow: the request is written for you, and it and the reply are published there.
  3. Got a permit already? Send it to us and the works will be assessed.

Why this matters for reading spills

Works over capacity

If a works cannot treat the flow it receives, it spills to protect itself. The remedy is capital investment or a lower permitted load — years and millions, but it is the water company's to fix.

Headroom, but still spills

A works with spare capacity whose network still spills points to another problem — often something on that branch, like a blockage, a failed pump, or groundwater getting into the sewer. Frequently cheap to fix, and fixable now.

No permit found

Where we cannot find the permitted flow, the works cannot be assessed at all. That is a gap in the public record, and closing it is the first step to holding capacity to account.

How growth becomes spills

A developer has a section 106 right to connect to the public sewer, and the water company has a section 94 duty to accept the flow — but capacity is only funded on a five-yearly capital cycle. New connections can therefore arrive years before the works is enlarged to take them, and the overflow absorbs the gap. Schedule 3 to the Flood and Water Management Act 2010, which would make sustainable drainage mandatory and give a SuDS Approving Body a say, has been in force in Wales since 2018 but remains uncommenced in England — so here there is no such body.

What the permit actually sets

The permitted dry-weather flow is set by Formula A — roughly DWF + 1,360 × population + 2 × trade effluent (litres/day). The permit also sets a flow to full treatment, typically about three times DWF, below which everything must be treated rather than spilled. Our load figure compares estimated demand against that permitted DWF. 29 works here have no permitted flow loaded in River Hub yet, so their load can’t be calculated: they show as not assessed, never 0%.