Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

51
Measures in this catchment
WINEP, current record
50
Still active
not yet past their date
1
Assumed complete
completion date has passed
11
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SW101550 · aWFD_NDNo deterioration
P limit of 3.3mg/l
HIGHAMPTON_STW_HATHERLEIGH
Complete 2025-26Pulworthy Brook
08SW104994 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
ABBOTSHAM STW
Due 2026-27Kenwith Stream
08SW104993 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
ABBOTSHAM STW
Due 2026-27Kenwith Stream
08SW104978 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
BEAFORD WASTE WTW
Due 2026-27Woolleigh Brook
08SW104963 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
BLACK TORRINGTON STW
Due 2026-27Torridge (Combe Lake to Lew)
08SW104964 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BLACK TORRINGTON STW
Due 2026-27Torridge (Combe Lake to Lew)
08SW104952 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Bradworthy STW
Due 2026-27Waldon
08SW104951 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Bradworthy STW
Due 2026-27Waldon
08SW104930 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BUCKLAND BREWER STW
Due 2026-27Duntz
08SW104929 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
BUCKLAND BREWER STW
Due 2026-27Duntz
08SW104865 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
DOLTON SEWAGE TREATMENT WORKS
Due 2026-27Dolton Stream
08SW104864 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
DOLTON SEWAGE TREATMENT WORKS
Due 2026-27Dolton Stream
08SW104846 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
EXBOURNE STW
Due 2026-27Hole Brook
08SW104845 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
EXBOURNE STW
Due 2026-27Hole Brook
08SW104817 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
GREAT TORRINGTON STW
Due 2026-27Torridge (Lew to Estuary)
08SW104818 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
GREAT TORRINGTON STW
Due 2026-27Torridge (Lew to Estuary)
08SW104804 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Hatherleigh STW
Due 2026-27Lower River Lew (Torridge)
08SW104803 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Hatherleigh STW
Due 2026-27Lower River Lew (Torridge)
08SW104307 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
MERTON STW
Due 2026-27Upper River Mere
08SW104315 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
MERTON STW
Due 2026-27Upper River Mere
08SW104695 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
NORTHLEW SEWAGE TREATMENT WORKS
Due 2026-27Northlew Stream
08SW104694 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
NORTHLEW SEWAGE TREATMENT WORKS
Due 2026-27Northlew Stream
08SW104690 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
OKEHAMPTON STW
Due 2026-27Middle River Okement
08SW104691 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
OKEHAMPTON STW
Due 2026-27Middle River Okement
08SW104687 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
PARKHAM STW
Due 2026-27Upper River Yeo (Bideford)
08SW104686 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
PARKHAM STW
Due 2026-27Upper River Yeo (Bideford)
08SW104679 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
PETROCKSTOWE STW
Due 2026-27Little Mere River
08SW104678 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
PETROCKSTOWE STW
Due 2026-27Little Mere River
08SW104647 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
SAMPFORD COURTENAY STW
Due 2026-27Hole Brook
08SW104648 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
SAMPFORD COURTNEY STW
Due 2026-27Hole Brook
08SW104639 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
SHEBBEAR STW
Due 2026-27Torridge (Combe Lake to Lew)
08SW104640 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
SHEBBEAR STW
Due 2026-27Torridge (Combe Lake to Lew)
08SW104314 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
SHEEPWASH STW
Due 2026-27Torridge (Combe Lake to Lew)
08SW104305 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
SHEEPWASH STW
Due 2026-27Torridge (Combe Lake to Lew)
08SW104529 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
WOOLFARDISWORTHY STW
Due 2026-27Dipple Water
08SW104530 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
WOOLFARDISWORTHY STW
Due 2026-27Dipple Water
08SW104999 · fzEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
ABBOTSHAM STW_SO_ABBOTSHAM
Due 2027-28ABBOTSHAM STW_SO_ABBOTSHAM
08SW100189 · aWFD_INVInvestigation
*Holding Line* investigation to inform potential requirements for AMP9
HORNS CROSS STW, FORD & FAIRY CROSS STW, WOODTOWN STW, LITTLEHAM STW
Due 2027-28Upper River Yeo (Bideford)
08SW100193 · aWFD_INVInvestigation
*Holding Line* investigation to inform potential requirements for AMP9
SAMPFORD COURTENAY STW, SAMPFORD CHAPPLE STW, EXBOURNE STW, MONKOKEHAMPTON STW, BROADWOODKELLY STW
Due 2027-28Hole Brook
08SW105000 · aSW_NDNo deterioration
10 Spills 50m3 (add to existing Taw/Torridge 01A)
BUCKLEIGH SPS_PSCSOEO_NORTHAM
Due 2027-28BUCKLEIGH SPS_PSCSOEO_NORTHAM
08SW101413 · aU_IMP4Improvement
Reduction of spills to meet EnvAct_IMP drivers
ABBOTSHAM STW_SO_ABBOTSHAM
Due 2027-28ABBOTSHAM STW_SO_ABBOTSHAM
08SW104292 · aU_IMP4Improvement
To comply with UWWTR
HATHERLEIGH BRIDGE_CSO_HATHERLEIGH
Due 2027-28HATHERLEIGH BRIDGE_CSO_HATHERLEIGH
08SW104293 · aU_IMP4Improvement
To comply with UWWTR
MANOR HALL_CSO_HATHERLEIGH
Due 2027-28MANOR HALL_CSO_HATHERLEIGH
08SW100054 · aWFD_IMPgImprovement
New or tightened P consent
PARKHAM_STW_PARKHAM
Due 2029-30Upper River Yeo (Bideford)
08SW102113 · alU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
FOLLY GATE_STW_FOLLY GATE
Due 2030-31West Okement
08SW102100 · fU_IMP1Improvement
Increased monitoring
HILL BARTON_STW_OKEHAMPTON
Due 2030-31Middle River Okement
08SW102113 · oU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
LITTLEHAM_STW_LITTLEHAM
Due 2030-31Upper River Yeo (Bideford)
08SW102113 · qU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
MERTON_STW_MERTON
Due 2030-31Upper River Mere
08SW102113 · uU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
SHEEPWASH_STW_SHEEPWASH
Due 2030-31Torridge (Combe Lake to Lew)
08SW102113 · xU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
STIBB CROSS_STW_TORRINGTON
Due 2030-31Combe Lake
08SW102113 · acU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
SUTCOMBE MILL_STW_SUTCOMBE
Due 2030-31Waldon

51 of 51 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.