An overflow that spills while its own treatment works stays shut is not being overwhelmed by rain — the problem is upstream of the works, and local.

If the sewer network were genuinely overwhelmed by rainfall, the treatment works' own storm overflow would be discharging too.

When an upstream overflow spills on a day its works did not, the works still had capacity — so the discharge points to a blockage, a failed pump, or infiltration on that branch, not to a works too small for its catchment. That changes who pays and how fast: a branch fault is maintenance, chargeable now, not a capital scheme waiting for the next five-year price review.

OverflowEventsIts worksOn record
Old Cleeve Bye Farm NewSO240Watchet STWNo measure
HawkwellSO200Minehead STWNo measure
Sampford Brett Sampford BrettSO86Watchet STWNo measure
Watchet Mill StreetSO80Watchet STWNo measure
CowbridgeSO78Minehead STWNo measure
BicknollerSO67Watchet STWNo measure
Monksilver B318858Watchet STWNo measure
Bilbrook49Minehead STWNo measure
Williton Union LaneSO46Watchet STWNo measure
Blue Anchor Pill Bridge37Minehead STWNo measure
Wootton Courtenay18Minehead STWNo measure
PorlockSO7Porlock STWNo measure
StogumberSO5Watchet STWNo measure

What this needs to be reliable

The comparison needs both monitors working. Where a works' own overflow monitor was offline we record no result rather than a pre-works spill, so this is a floor. A treatment works itself is excluded — it is the end of the line and cannot spill before the works. Two works in the catchment have no monitored overflow at all, so their upstream overflows are listed as not assessed, not as clean.