Who is fixing it

Reduction tracker

Is each overflow actually spilling less? The reduction plan won't tell you per overflow — so we measure it from the spill record.

What the plan is, and what it leaves out

The Storm Overflows Discharge Reduction Plan is the government's plan — published in 2022 and expanded in September 2023 — to cut how often England's storm overflows discharge. It sets deadlines by category, not by overflow:

  • By 2035 — overflows near every designated bathing water, and 75% of those near high-priority nature sites, must be improved.
  • By 2045 — the remaining high-priority overflows.
  • By 2050 — every storm overflow, with discharges capped at around 10 spills a year regardless of location.

The targets are due to be reviewed in 2027 — a commitment in the plan, not a statutory duty. But the plan sets no target for any individual overflow and publishes no per-overflow progress — only these whole-category deadlines, and it doesn't even publish which specific overflows are high-priority. So there is no official way to ask “is this overflow on track?” This page builds that view from the Environment Agency's EDM record: each overflow's counted spills per year — the EA's own 12/24-hour block figure, the same basis the cap is written in — against its 2020 baseline and the 2050 cap of ~10, with the deadline its location implies.

14
Above the 2050 cap
of 23 tracked
5
Rising since baseline
trend is the wrong way
0
On a 2035 deadline
near a bathing water
9
Within the cap
≤10 spills in 2025

Every overflow against its cap

Ranked by the latest full year's spills. The deadline is derived from proximity to a designated site — indicative, not an official per-overflow target. The dotted line on each trajectory is the 10-spills cap.

OverflowDeadlineBaselineLatestSince baselinevs capTrajectoryVerdict
Diptford STWSO
SBB00364
2050143 ·24
111
154 events
-22%11.1×Falling — behind
Moreleigh STWSO
SBB00804
2050123 ·24
92
154 events
-25%9.2×Falling — behind
Comminutor House Gould Rd, SalcombeCSO
SBB00298
2050136
89
188 events
-35%8.9×Falling — behind
South Brent STWSO
SBB01097
205085
66
27 events
-22%6.6×Falling — behind
Bridge Street, KingsbridgeCSO
SBB00156
205010
50
79 events
+400%5×Rising
Sherford STWSO
SBB01077
2050161
50
45 events
-69%5×Falling — behind
East Allington STWSSO
SBB00389
20501
40
32 events
+3900%4×Rising
Brent Mill, South BrentCSO
SBB00150
205019
36
78 events
+89%3.6×Rising
Prince of Wales Rd, KingsbridgeCSO
SBB00984
205059
35
50 events
-41%3.5×Falling — behind
Ditch End S T, East PortlemouthPS-CSO/EO
SBB00394
205048
29
122 events
-40%2.9×Falling — behind
Chillington STWSSO
SBB00244
20506
28
33 events
+367%2.8×Rising
Meadowside ChillingtonCSO
SBB00246
205021
25
20 events
+19%2.5×Rising
Batson pumping station, SalcombePS-CSO/EO
SBB00080
205041
17
18 events
-59%1.7×Falling — behind
Loddiswell STWSSO
SBB00700
205063
15
30 events
-76%1.5×Nearly there
Southville pumping station, KingsbridgePS-CSO/EO
SBB01109
205012
8
4 events
-33%0.8×Within the cap
Shadycombe Tk Lower Tunnels, SalcombeCSO
SBB01073
205015
7
3 events
-53%0.7×Within the cap
Shadycombe Tank Csoeo, Salcombe
SBB01072
20504
4
8 events
0%0.4×Within the cap
Aveton Gifford STWSSO
SBB00057
205016
4
4 events
-75%0.4×Within the cap
Chillington pumping stationPS-CSO/EO
SBB00585
20502 ·24
2
1 events
0%0.2×Within the cap
North Sands pumping station, SalcombePS-CSO/EO
SBB00846
20505
1
0 events
-80%0.1×Within the cap
Westville pumping station, KingsbridgePS-CSO/EO
SBB01354
205010
0
0 events
-100%0×Within the cap
South Sands pumping station, SalcombePS-CSO/EO
SBB01103
20506
0
0 events
-100%0×Within the cap
Heather Park, South BrentPS-CSO/EO
SBB00555
20500 ·23
0
0 events
—0×—Within the cap

What this is — and what it is not

This is River Hub's measurement, not the plan's. The reduction plan publishes no target for an individual overflow and no per-overflow progress — so we compare each outlet's counted spills to its 2020 baseline and the 10/year cap. Counted spills use the Environment Agency's 12/24-hour block method — the figure the cap is actually written in — taken from the published annual return where we have it and computed the same way for the current year; the smaller “events” figure beneath each is River Hub's count of discrete discharges over 15 minutes, shown for context. The deadline shown is derived by proximity to a designated site, not an official determination, and the plan is a policy commitment rather than a statutory duty. A falling trend is progress, but only ≤10 by the deadline is compliance. Where 2020 data is thin the baseline falls back to the earliest year on record, shown beside it. How the two counts differ →