Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

36
Measures in this catchment
WINEP, current record
36
Still active
not yet past their date
0
Assumed complete
completion date has passed
4
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SW104984 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
AYLESBEARE STW
Due 2026-27Aylesbeare stream
08SW104983 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
AYLESBEARE STW
Due 2026-27Aylesbeare stream
08SW104954 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BRADNINCH STW
Due 2026-27Lower Culm
08SW104953 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
BRADNINCH STW
Due 2026-27Lower Culm
08SW104923 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
BURLESCOMBE + WESTLEIGH STW
Due 2026-27Spratford Stream
08SW104924 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BURLESCOMBE + WESTLEIGH STW
Due 2026-27Spratford Stream
08SW104873 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
CULMSTOCK SEWAGE TREATMENT WORKS
Due 2026-27Middle Culm
08SW104874 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
CULMSTOCK SEWAGE TREATMENT WORKS
Due 2026-27Middle Culm
08SW104861 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Dunkeswell STW
Due 2026-27Madford River
08SW104860 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Dunkeswell STW
Due 2026-27Madford River
08SW104498 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Halberton STW
Due 2026-27Halberton Stream
08SW104499 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Halberton STW
Due 2026-27Halberton Stream
08SW104792 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Hemyock STW
Due 2026-27Middle Culm
08SW104791 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Hemyock STW
Due 2026-27Middle Culm
08SW104786 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
HOLCOMBE ROGUS STW
Due 2026-27Spratford Stream
08SW104785 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
HOLCOMBE ROGUS STW
Due 2026-27Spratford Stream
08SW104668 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
PLYMTREE STW
Due 2026-27Upper Clyst
08SW104667 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
PLYMTREE STW
Due 2026-27Upper Clyst
08SW104651 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
REWE + STOKE CANON
Due 2026-27Lower Culm
08SW104652 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
REWE + STOKE CANON
Due 2026-27Lower Culm
08SW104646 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
SAMPFORD PEVERELL STW
Due 2026-27Spratford Stream
08SW104645 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
SAMPFORD PEVERELL STW
Due 2026-27Spratford Stream
08SW104638 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
SILVERTON STW
Due 2026-27Lower Culm
08SW104637 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
SILVERTON STW
Due 2026-27Lower Culm
08SW104559 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
UFFCULME STW
Due 2026-27Lower Culm
08SW104560 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
UFFCULME STW
Due 2026-27Lower Culm
08SW104542 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Willand STW
Due 2026-27Lower Culm
08SW104541 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Willand STW
Due 2026-27Lower Culm
08SW104531 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
WOODBURY STW
Due 2026-27Polly Brook
08SW104532 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
WOODBURY STW
Due 2026-27Polly Brook
08SW102001 · aWFD_NDLS_Chem2No deterioration
Cypermethrin standstill permit limit
DUNKESWELL_STW_DUNKESWELL
Due 2026-27Madford River
08SW100186 · aWFD_INVInvestigation
Investigation to inform PR29
SPRATFORD STREAM
Due 2027-28Spratford Stream
08SW101000 · aWFD_IMPmImprovement
New or tightened P consent
AYLESBEARE_STW_AYLESBEARE
Due 2029-30Aylesbeare Stream
08SW102958 · aEE_IMPImprovement
Eel Abstraction
Eel Abstraction - River Exe (Bolham Pump House, Bolham)
Due 2029-30Bolham River
08SW101056 · aWFD_IMPgImprovement
New or tightened P consent
PLYMTREE_STW_PLYMTREE
Due 2029-30Upper Clyst
08SW102100 · jU_IMP1Improvement
First time UWWTR monitoring
HEMYOCK_STW_HEMYOCK
Due 2030-31Middle Culm

36 of 36 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.