What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08SW104984 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) AYLESBEARE STW | Due 2026-27 | Aylesbeare stream |
| 08SW104983 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) AYLESBEARE STW | Due 2026-27 | Aylesbeare stream |
| 08SW104954 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) BRADNINCH STW | Due 2026-27 | Lower Culm |
| 08SW104953 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) BRADNINCH STW | Due 2026-27 | Lower Culm |
| 08SW104923 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) BURLESCOMBE + WESTLEIGH STW | Due 2026-27 | Spratford Stream |
| 08SW104924 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) BURLESCOMBE + WESTLEIGH STW | Due 2026-27 | Spratford Stream |
| 08SW104873 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) CULMSTOCK SEWAGE TREATMENT WORKS | Due 2026-27 | Middle Culm |
| 08SW104874 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) CULMSTOCK SEWAGE TREATMENT WORKS | Due 2026-27 | Middle Culm |
| 08SW104861 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Dunkeswell STW | Due 2026-27 | Madford River |
| 08SW104860 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Dunkeswell STW | Due 2026-27 | Madford River |
| 08SW104498 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) Halberton STW | Due 2026-27 | Halberton Stream |
| 08SW104499 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Halberton STW | Due 2026-27 | Halberton Stream |
| 08SW104792 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Hemyock STW | Due 2026-27 | Middle Culm |
| 08SW104791 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) Hemyock STW | Due 2026-27 | Middle Culm |
| 08SW104786 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) HOLCOMBE ROGUS STW | Due 2026-27 | Spratford Stream |
| 08SW104785 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) HOLCOMBE ROGUS STW | Due 2026-27 | Spratford Stream |
| 08SW104668 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) PLYMTREE STW | Due 2026-27 | Upper Clyst |
| 08SW104667 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) PLYMTREE STW | Due 2026-27 | Upper Clyst |
| 08SW104651 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) REWE + STOKE CANON | Due 2026-27 | Lower Culm |
| 08SW104652 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) REWE + STOKE CANON | Due 2026-27 | Lower Culm |
| 08SW104646 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) SAMPFORD PEVERELL STW | Due 2026-27 | Spratford Stream |
| 08SW104645 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) SAMPFORD PEVERELL STW | Due 2026-27 | Spratford Stream |
| 08SW104638 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) SILVERTON STW | Due 2026-27 | Lower Culm |
| 08SW104637 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) SILVERTON STW | Due 2026-27 | Lower Culm |
| 08SW104559 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) UFFCULME STW | Due 2026-27 | Lower Culm |
| 08SW104560 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) UFFCULME STW | Due 2026-27 | Lower Culm |
| 08SW104542 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Willand STW | Due 2026-27 | Lower Culm |
| 08SW104541 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Willand STW | Due 2026-27 | Lower Culm |
| 08SW104531 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) WOODBURY STW | Due 2026-27 | Polly Brook |
| 08SW104532 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) WOODBURY STW | Due 2026-27 | Polly Brook |
| 08SW102001 · a | WFD_NDLS_Chem2 | No deterioration | Cypermethrin standstill permit limit DUNKESWELL_STW_DUNKESWELL | Due 2026-27 | Madford River |
| 08SW100186 · a | WFD_INV | Investigation | Investigation to inform PR29 SPRATFORD STREAM | Due 2027-28 | Spratford Stream |
| 08SW101000 · a | WFD_IMPm | Improvement | New or tightened P consent AYLESBEARE_STW_AYLESBEARE | Due 2029-30 | Aylesbeare Stream |
| 08SW102958 · a | EE_IMP | Improvement | Eel Abstraction Eel Abstraction - River Exe (Bolham Pump House, Bolham) | Due 2029-30 | Bolham River |
| 08SW101056 · a | WFD_IMPg | Improvement | New or tightened P consent PLYMTREE_STW_PLYMTREE | Due 2029-30 | Upper Clyst |
| 08SW102100 · j | U_IMP1 | Improvement | First time UWWTR monitoring HEMYOCK_STW_HEMYOCK | Due 2030-31 | Middle Culm |
36 of 36 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.