Treatment works capacity
Every overflow goes to a sewage treatment works that serves a fixed area. There is no public data available to understand if the works has sufficient capacity to treat the sewage for the local population. We estimate this capacity based on the required capacity in the EA permit compared to the local population estimated to be on the sewage system. As we receive data on the actual processing capacity from South West Water we will add that too.
Capacity across the Looe & Seaton
Not yet known whether the Looe & Seaton’s 6 treatment works are big enough
They serve about 8,826 people. Judging capacity needs each works’ permitted flow, and River Hub hasn’t loaded those permits for the Looe & Seaton. That is a gap in what River Hub holds, not a finding about the works.
The black line marks 100% of permitted dry-weather flow; a dashed empty bar means no permit was found to measure against. Load is an estimate — population served × per-head water use, plus infiltration — not a permit-compliance finding. A works over 100% here is a signal to investigate, not a proven breach. Overflow hours are the works' own storm overflow in the last full year.
6 works with no permit loaded
River Hub doesn’t yet hold the permits for Trewidland STW, Crows Nest STW, Widegates STW, Duloe STW, Minions STW, Tredinnick STW, so it can’t check whether they are big enough for the people they serve. That’s a gap, not a clean bill of health, and it’s the quickest thing on this page to fix: discharge permits are public, and the Environment Agency must supply them on request. No request for them has been published on River Hub yet.
- Look a works up on the EA’s public register of discharge permits.
- Ask the Environment Agency for them through WhatDoTheyKnow: the request is written for you, and it and the reply are published there.
- Got a permit already? Send it to us and the works will be assessed.
Why this matters for reading spills
Works over capacity
If a works cannot treat the flow it receives, it spills to protect itself. The remedy is capital investment or a lower permitted load — years and millions, but it is the water company's to fix.
Headroom, but still spills
A works with spare capacity whose network still spills points to another problem — often something on that branch, like a blockage, a failed pump, or groundwater getting into the sewer. Frequently cheap to fix, and fixable now.
No permit found
Where we cannot find the permitted flow, the works cannot be assessed at all. That is a gap in the public record, and closing it is the first step to holding capacity to account.
How growth becomes spills
A developer has a section 106 right to connect to the public sewer, and the water company has a section 94 duty to accept the flow — but capacity is only funded on a five-yearly capital cycle. New connections can therefore arrive years before the works is enlarged to take them, and the overflow absorbs the gap. Schedule 3 to the Flood and Water Management Act 2010, which would make sustainable drainage mandatory and give a SuDS Approving Body a say, has been in force in Wales since 2018 but remains uncommenced in England — so here there is no such body.
What the permit actually sets
The permitted dry-weather flow is set by Formula A — roughly DWF + 1,360 × population + 2 × trade effluent (litres/day). The permit also sets a flow to full treatment, typically about three times DWF, below which everything must be treated rather than spilled. Our load figure compares estimated demand against that permitted DWF. 6 works here have no permitted flow loaded in River Hub yet, so their load can’t be calculated: they show as not assessed, never 0%.