Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

22
Measures in this catchment
WINEP, current record
22
Still active
not yet past their date
0
Assumed complete
completion date has passed
6
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SO102407 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Boldre WTW
Due 2026-27BOLDRE
08SO102695 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
BOLDRE WWTW
Due 2026-27Lymington River
08SO102408 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Brockenhurst WTW
Due 2026-27Lymington River
08SO102700 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
BROCKENHURST WWTW
Due 2026-27Lymington River
08SO102414 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
East Boldre WTW
Due 2026-27EAST BOLDRE
08SO102731 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
EAST BOLDRE WWTW
Due 2026-27Hatchet Stream
08SO102487 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Flexford Lane Sway WTW
Due 2026-27Avon Water
08SO102748 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
FLEXFORD LANE SWAY WWTW
Due 2026-27Avon Water
08SO102434 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Lyndhurst WTW
Due 2026-27LYNDHURST SSO - 115810
08SO102804 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
LYNDHURST WWTW
Due 2026-27Beaulieu
08SO104950 · gsEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
BECTON LANE BARTON ON SEA CEO
Due 2027-28Becton Bunny
08SO100043 · gEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
BROCKENHURST CSO
Due 2027-28LYMINGTON RIVER
08SO104950 · paEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
BROCKENHURST SSO
Due 2027-28Lymington River
08SO104950 · xEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
FLEXFORD LANE SWAY SSO
Due 2027-28Avon Water
08SO104950 · afEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
LYNDHURST SSO
Due 2027-28Beaulieu
08SO102615 · aWFD_INV_N-TalInvestigation
Investigation to assess treatment options for nitrogen. Full-scale trial, Optimise MLE
Milford Road Pennington WTW
Due 2027-28Avon Water
08SO104003 · aHD_IMP_NNImprovement
Amend permit limit of Total N to 37.80 mg/l
Brockenhurst WwTW
Due 2029-30Lymington River
08SO102633 · aSSSI_IMPImprovement
N reduction
East End WwTW
Due 2029-30Sowley Stream
08SO103975 · aHD_IMP_NNImprovement
Amend permit limit of Total N to 10 mg/l
FLEXFORD LANE SWAY
Due 2029-30Avon Water
08SO103983 · aHD_IMP_NNImprovement
Amend permit limit of Total N to 10 mg/l
LYNDHURST
Due 2029-30Beaulieu
08SO100089 · aEnvAct_IMP4Improvement
Wetland + Lining
BROCKENHURST CSO
Due 2034-35LYMINGTON RIVER
08SO103963 · aEnvAct_IMP2Improvement
Wetland + Lining
BROCKENHURST SSO
Due 2034-35Lymington River

22 of 22 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.