Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

36
Measures in this catchment
WINEP, current record
36
Still active
not yet past their date
0
Assumed complete
completion date has passed
11
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SW104311 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
BOYTON STW
Due 2026-27Tamar (River Ottery to River Deer)
08SW104942 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Bridgerule STW
Due 2026-27Tamar (Small Brook to River Deer)
08SW104941 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Bridgerule STW
Due 2026-27Tamar (Small Brook to River Deer)
08SW104309 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
EGLOSKERRY STW
Due 2026-27Kensey
08SW104317 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
EGLOSKERRY STW
Due 2026-27Kensey
08SW104813 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
HALWILL SEWAGE TREATMENT WORKS
Due 2026-27Carey
08SW104814 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
HALWILL SEWAGE TREATMENT WORKS
Due 2026-27Carey
08SW104784 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Holsworthy (Derriton) STW
Due 2026-27Deer
08SW104783 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Holsworthy (Derriton) STW
Due 2026-27Deer
08SW104758 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
LAUNCESTON (ST LEONARDS) STW
Due 2026-27Kensey
08SW104759 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
LAUNCESTON (ST LEONARDS) STW
Due 2026-27Kensey
08SW104699 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
NORTH PETHERWIN STW
Due 2026-27Bolesbridge Water
08SW104698 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
NORTH PETHERWIN STW
Due 2026-27Bolesbridge Water
08SW104654 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
PYWORTHY SEWAGE TREATMENT WORKS
Due 2026-27Derril Water
08SW104653 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
PYWORTHY SEWAGE TREATMENT WORKS
Due 2026-27Derril Water
08SW100019 · dWFD_INV_WRHMWBInvestigation
Investigation and options appraisal to review impact of reservoir on habitat and flows
Upper Tamar Lake
Due 2026-27Upper River Tamar
08SW102001 · bWFD_NDLS_Chem2No deterioration
Cypermethrin standstill permit limit
DERRITON_STW_HOLSWORTHY
Due 2026-27Deer
08SW104999 · asEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
DERRITON STW_SO_HOLSWORTHY
Due 2027-28DERRITON STW_SO_HOLSWORTHY
08SW100192 · aWFD_INVInvestigation
*Holding Line* investigation to inform potential requirements for AMP9
DERRITON STW, SLATE COURT STW, CANAL FARM STW
Due 2027-28Deer
08SW104999 · ayEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
EGLOSKERRY SPS_PSCSOEO_LAUNCESTON
Due 2027-28EGLOSKERRY SPS_PSCSOEO_LAUNCESTON
08SW104999 · bxEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
LANGORE SPS_PSCSOEO_LAUNCESTON
Due 2027-28LANGORE SPS_PSCSOEO_LAUNCESTON
08SW104285 · fEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
NORTH PETHERWIN STW_SO_NORTH PETHERWIN
Due 2027-28NORTH PETHERWIN STW_SO_NORTH PETHERWIN
08SW104999 · icEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
ST LEONARDS STW_SSO_LAUNCESTON
Due 2027-28ST LEONARDS STW_SSO_LAUNCESTON
08SW104999 · fhEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
YEOLMBRIDGE SPST_PSCSOEO_YEOLMBRIDGE
Due 2027-28YEOLMBRIDGE SPST_PSCSOEO_YEOLMBRIDGE
08SW104999 · fiEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
YEOLMBRIDGE_CSO_YEOLMBRIDGE
Due 2027-28YEOLMBRIDGE_CSO_YEOLMBRIDGE
08SW100095 · aEnvAct_IMP2Improvement
Reduction of spills to meet EnvAct_IMP drivers
DERRITON STW_SO_HOLSWORTHY
Due 2029-30DERRITON STW_SO_HOLSWORTHY
08SW100096 · aEnvAct_IMP2Improvement
Reduction of spills to meet EnvAct_IMP drivers
DERRITON STW_SSO_HOLSWORTHY
Due 2029-30DERRITON STW_SSO_HOLSWORTHY
08SW101532 · aWFD_IMPgImprovement
New or tightened P consent
HALWILL_STW_HALWILL
Due 2029-30Carey
08SW101059 · aWFD_IMPgImprovement
New or tightened P consent
PYWORTHY_STW_PYWORTHY
Due 2029-30Derril Water
08SW102113 · fU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
BOYTON_STW_BOYTON
Due 2030-31Tamar (River Ottery to River Deer)
08SW102113 · iU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
CANAL FARM_STW_CHILSWORTHY
Due 2030-31Deer
08SW102113 · kU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
EGLOSKERRY_STW_EGLOSKERRY
Due 2030-31Kensey
08SW102148 · aU_IMP2Improvement
Already had P stripping WFD will require Monitoring only
ST LEONARDS_STW_LAUNCESTON
Due 2030-31Tamar (River Ottery to River Lyd)
08SW102113 · afU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
WARBSTOW_STW_WARBSTOW
Due 2030-31Canworthy Water
08SW102113 · aiU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
WHITSTONE_STW_WHITSTONE
Due 2030-31Tamar (Small Brook to River Deer)
08SW102113 · ajU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
YEOLMBRIDGE_STW_YEOLMBRIDGE
Due 2030-31Lower River Ottery

36 of 36 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.