What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08SO104731 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils Bognor Main | Due 2026-27 | Aldingbourne Rife |
| 08SO102694 · a | U_MON3 | Monitoring | U_MON3b: MCERTS certified overflow operation monitor Bognor Main WPS | Due 2026-27 | Aldingbourne Rife |
| 08SO102493 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils Lavant WTW | Due 2026-27 | Lavant (Sussex) |
| 08SO102791 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor LAVANT WWTW | Due 2026-27 | Lavant (Sussex) |
| 08SO102433 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Lidsey WTW | Due 2026-27 | Lidsey Rife |
| 08SO102794 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor LIDSEY WWTW | Due 2026-27 | Lidsey Rife |
| 08SO102499 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils Sidlesham WTW | Due 2026-27 | Broad Rife |
| 08SO102873 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor SIDLESHAM WWTW | Due 2026-27 | Broad Rife |
| 08SO102527 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Summer Lane Pagham WTW | Due 2026-27 | Pagham Rife |
| 08SO102897 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor SUMMER LANE PAGHAM WWTW | Due 2026-27 | Pagham Rife |
| 08SO104733 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Tangmere WTW | Due 2026-27 | Aldingbourne Rife |
| 08SO102900 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor TANGMERE WWTW | Due 2026-27 | Aldingbourne Rife |
| 08SO101180 · a | BW_ND | No deterioration | SuDS and storage. Costings are based on the least cost option, which is a 30m3 storage tank. However, SuDS will be explored first to maximise green options before sizing any storage needed to achieve the spill requirements of 2 or less spills per bathing water season. Note: Overflow discharges to inalnd watercourse, but as the reason is for bathing waters, a EnvAct_IMP3 secondary driver has been assigned. Bognor Main CEO | Due 2026-27 | Aldingbourne Rife |
| 08SO101101 · c | WFD_NDLS_Chem1 | No deterioration | Prevent any deterioration Tangmere WTW | Due 2026-27 | Aldingbourne Rife |
| 08SO104950 · op | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact LAVANT NO. SSO | Due 2027-28 | Lavant (Sussex) |
| 08SO104950 · bb | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact LIDSEY SSO | Due 2027-28 | LIDSEY RIFE |
| 08SO104950 · rh | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact MARSHALL CLOSE BARNHAM CSO | Due 2027-28 | Lidsey Rife |
| 08SO103818 · a | WFD_INV | Investigation | Investigations for actions to improve water quality in terms of relevant WFD status objectives. SIDLESHAM WTW | Due 2027-28 | Broad Rife |
| 08SO104950 · l | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the Shellfish Water and ensure no more than 10 spills per annum (on average) as an agglomeration SINGLETON RELIEF CEO | Due 2027-28 | Lavant (Sussex) |
| 08SO104950 · pq | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact SUMMER LANE PAGHAM SSO | Due 2027-28 | Pagham Rife |
| 08SO100043 · cv | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact TANGMERE SSO | Due 2027-28 | ALDINGBOURNE RIFE |
| 08SO104029 · a | WFD_INV | Investigation | Investigate the cause of the spills Tangmere WTW WFD_INV | Due 2027-28 | Aldingbourne Rife |
| 08SO103964 · a | SW_ND | No deterioration | Wetland + Lining SINGLETON RELIEF CEO | Due 2027-28 | Lavant (Sussex) |
| 08SO103980 · a | HD_IMP_NN | Improvement | Amend permit limit of Total N to 10 mg/l LAVANT WWTW | Due 2029-30 | Lavant (Sussex) |
| 08SO104042 · a | WFD_ND | No deterioration | Amend WFD ND BOD permit LIDSEY | Due 2029-30 | Lidsey Rife |
| 08SO100198 · a | EnvAct_IMP2 | Improvement | Currently meets Defra rainfall target but may need <0 spill solution to prevent ecological harm TANGMERE SSO | Due 2029-30 | ALDINGBOURNE RIFE |
| 08SO101101 · b | WFD_IMP_CHEM | Improvement | Deliver a physical improvement Tangmere WTW | Due 2029-30 | Aldingbourne Rife |
| 08SO101101 · a | WFD_ND_CHEM4 | No deterioration | Prevent any deterioration Tangmere WTW | Due 2029-30 | Aldingbourne Rife |
| 08SO100999 · a | U_IMP1 | Improvement | Actions to improve discharges from agglomerations that, through population growth, have crossed the population thresholds in the UWWTR and therefore must achieve more stringent UWWTR requirements. This includes newly qualifying discharges (from agglomerations >10,000population equivalent (PE)) within existing Sensitive Areas. This includes discharges of >2,000 PE to fresh waters and estuaries and discharges >10,000 PE to coastal waters, as well as discharges >10,000 PE and 100,000 PE to Sensitive Areas. Summer Lane Pagham WWTW | Due 2030-31 | Pagham Rife |
| 08SO103956 · a | EnvAct_IMP2 | Improvement | Wetland + Lining LAVANT NO SSO | Due 2034-35 | Lavant (Sussex) |
| 08SO103958 · a | EnvAct_IMP4 | Improvement | Wetland + Lining LIDSEY SSO | Due 2034-35 | Lidsey Rife |
| 08SO103929 · a | EnvAct_IMP2 | Improvement | Preferred option is SuDS and Storage, but costs based on storage only MARSHALL CLOSE BARNHAM CSO | Due 2034-35 | Lidsey Rife |
| 08SO103914 · a | EnvAct_IMP2 | Improvement | SuDS + Storage SUMMER LANE PAGHAM SSO | Due 2034-35 | Pagham Rife |
33 of 33 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.